5714 N BUFFALO AVE 91401

Certificate Information: 5714 N BUFFALO AVE 91401

Application / Permit
22014-20000-02691
Plan Check / Job No.
B22VN08500
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan PROPOSED 1 STORY ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING TO NEW FAMILY ROOM, INTERIOR REMODEL.
Permit Issued
Issued on 10/17/2022
Issuing Office
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2022 APPLICANT
Assigned to Plan Check Engineer 6/10/2022 MICHAEL LOPEZ
Corrections Issued 6/10/2022 MICHAEL LOPEZ
Applicant returned to address corrections 8/12/2022 MICHAEL LOPEZ
Applicant returned to address corrections 8/30/2022 MICHAEL LOPEZ
Plan Check Approved 9/6/2022 MICHAEL LOPEZ
Issued 10/17/2022 APPLICANT
CofO in Progress 8/10/2023 RYAN SALAZAR
No Progress 9/19/2023 ROBERT GOLD
CofO in Progress 9/19/2023 ROBERT GOLD
CofO in Progress 1/16/2025 RYAN SALAZAR
No Progress 1/17/2025 RAUL OLAGI
CofO in Progress 1/17/2025 RAUL OLAGI
Permit Finaled 6/20/2025 RUBEN SALAS
Permit Finaled 6/20/2025 RUBEN SALAS
CofO Issued 6/20/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 8/4/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/9/2022 COLIN LOREDO
Sewer availability Cleared 8/9/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/12/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Hsiao,, Stephanie; Lic. No.: C75937 351 DAROCA AVE      LONG BEACH, CA 90803

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/28/2022 Approved WILLIAM WREN
Deputy Drilled-In Anchors 11/10/2022 Conditional Approval MICHAEL SMITH
Deputy Steel/Welding 11/10/2022 Conditional Approval RICHARD DOCKUS
BUILDING-Rough-Frame 11/22/2022 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval RYAN SALAZAR
Green Building Rough 11/22/2022 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 11/30/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 12/20/2022 Approved RYAN SALAZAR
HVAC-Rough 12/20/2022 Approved RYAN SALAZAR
PLUMBING-Rough 12/20/2022 Approved RYAN SALAZAR
Insulation 1/3/2023 Conditional Approval RYAN SALAZAR
Interior/Exterior Lathing 1/3/2023 Partial Approval RYAN SALAZAR
Shower Pan 1/10/2023 Not Ready for Inspection JOHN COLEMAN
Shower Pan 1/11/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/12/2023 Partial Approval THOMAS FINNILA
Drywall Nailing 1/13/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 6/23/2023 Approved RYAN SALAZAR
Final 6/23/2023 Corrections Issued RYAN SALAZAR
Green Building Final 6/23/2023 Approved RYAN SALAZAR
Green Building Rough 6/23/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 6/23/2023 Approved RYAN SALAZAR
Final 8/10/2023 Partial Approval RYAN SALAZAR
Special/Order Compliance 9/19/2023 Corrections Issued RYAN SALAZAR
Final 1/16/2025 OK to Issue CofO RYAN SALAZAR
Special/Order Compliance 1/23/2025 Corrections Issued RYAN SALAZAR