11025 N DE GARMO AVE 91331

Certificate Information: 11025 N DE GARMO AVE 91331

Application / Permit
22014-20000-02688
Plan Check / Job No.
B22VN08498
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
24'-7" x 8'-2" ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING- ALL WORK PER WFPP *****COMPLY WITH DEPARTMENT ORDER effective date 12/01/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 7/25/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 DANIEL ABRAMYAN
Corrections Issued 6/2/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 7/11/2022 DANIEL ABRAMYAN
Plan Check Approved 7/14/2022 DANIEL ABRAMYAN
Building Plans Picked Up 7/22/2022 APPLICANT
Issued 7/25/2022 APPLICANT
CofO in Progress 2/21/2023 LEO MILBAUER
CofO Issued 2/23/2023 DAVID JAMES
Permit Finaled 2/23/2023 DAVID JAMES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/21/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/21/2022 MEGAN GODINEZ
Sewer availability Cleared 6/21/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/21/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/21/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/21/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/26/2022 Conditional Approval MARK BEVELAQUA
Footing/Foundation/Slab 7/27/2022 Approved JASON BRANNON
METHANE-Barrier 7/27/2022 Approved JASON BRANNON
METHANE-Subgrade 7/27/2022 Approved JASON BRANNON
Insulation 8/3/2022 Partial Inspection JASON BRANNON
PLUMBING-Rough 8/3/2022 Partial Inspection JASON BRANNON
ELECTRICAL-Rough 8/17/2022 Approved JASON BRANNON
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Approved JASON BRANNON
PLUMBING-Rough 8/17/2022 Approved JASON BRANNON
Wood Frame 8/17/2022 Approved JASON BRANNON
Insulation 8/23/2022 Approved MARK BEVELAQUA
Drywall Nailing 8/26/2022 Approved JASON BRANNON
Interior/Exterior Lathing 8/26/2022 Approved JASON BRANNON
Interior/Exterior Lathing 8/30/2022 Approved JASON BRANNON
BUILDING-Rough-Frame 1/6/2023 Approved LEO MILBAUER
Final 1/6/2023 Not Ready for Inspection LEO MILBAUER
Green Building Final 1/6/2023 Approved LEO MILBAUER
Green Building Rough 1/6/2023 Approved LEO MILBAUER
METHANE-Final 1/6/2023 Approved LEO MILBAUER
METHANE-Rough 1/6/2023 Approved LEO MILBAUER
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Ready LEO MILBAUER
Smoke Detectors 1/6/2023 Approved LEO MILBAUER
ELECTRICAL-Final 1/26/2023 Approved LEO MILBAUER
Final 1/26/2023 Conditional Approval LEO MILBAUER
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Approved LEO MILBAUER