4936 N LOCKHAVEN AVE 90041

Certificate Information: 4936 N LOCKHAVEN AVE 90041

Application / Permit
22014-20000-02681
Plan Check / Job No.
B22VN08479
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO (E) 1-STORY SFD W/BASEMENT AND ADD A 2ND STORY ADDITION (1046 SQFT) AND (115 SQFT TO 1ST FOOR), ENCLOSE (E) PORCH INTO PART OF THE BASEMENT (249 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/24/2022
Issuing Office
Current Status
CofO Issued on 12/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 PETER MOSESIAN
Corrections Issued 7/2/2022 PETER MOSESIAN
Quality Review Completed 7/13/2022 OMID HEDAYAT
Building Plans Picked Up 7/14/2022 APPLICANT
Plan Check Approved 8/24/2022 PETER MOSESIAN
Issued 8/24/2022 APPLICANT
CofO in Progress 12/4/2025 DAVID WILLIAMS
Permit Finaled 12/6/2025 DEROLD HAUFF
CofO Issued 12/6/2025 DEROLD HAUFF
Permit Finaled 12/6/2025 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/19/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/19/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/19/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/19/2022 CINDY QI
BHO/Hillside ordinance Cleared 7/19/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/21/2022 CINDY QI
Sewer availability Cleared 7/21/2022 CINDY QI
Low Impact Development Cleared 8/4/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 8/8/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Barr,, Joseph Daniel; Lic. No.: C70708 1185 HERITAGE FARM RD      HICKORY, NC 28601
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Geologist Miller,, Jonathan Steven; Lic. No.: EG2391 24736 CALVERT STREET      WOODLAND HILLS, CA 91367

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/17/2022 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 12/7/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 12/7/2022 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 12/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 12/13/2022 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 12/20/2022 Not Ready for Inspection RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 1/3/2023 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/12/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/21/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 2/21/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 2/21/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 2/21/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/8/2023 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 3/8/2023 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 3/8/2023 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 3/8/2023 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 4/6/2023 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/26/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 4/26/2023 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Inspection CRAIG VAUGHAN
Gas Test 4/26/2023 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 4/26/2023 Approved CRAIG VAUGHAN
HVAC-Rough 4/26/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/26/2023 Corrections Issued CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 4/26/2023 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/26/2023 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 5/5/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 5/5/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Approved CRAIG VAUGHAN
Insulation 5/9/2023 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 5/12/2023 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/16/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/22/2023 Corrections Issued CRAIG VAUGHAN
Verify Sprinkler Sign Off 5/22/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 6/5/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 6/9/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/9/2023 Approved CRAIG VAUGHAN
Wood Frame 6/9/2023 Approved CRAIG VAUGHAN
Insulation 6/21/2023 Approved CRAIG VAUGHAN
Drywall Nailing 7/6/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/30/2023 Partial Approval JOAQUIN GREENOUGH
Shower Pan 8/30/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 11/8/2023 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 11/8/2023 Approved CRAIG VAUGHAN
HVAC-Final 11/8/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 11/8/2023 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 11/8/2023 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 11/17/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 11/17/2023 Approved CRAIG VAUGHAN
Service/Power Release 11/17/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 12/22/2023 Approved SCOTT FINNILA
Final 12/22/2023 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 12/22/2023 Approved SCOTT FINNILA
Green Building Final 12/22/2023 Approved SCOTT FINNILA
HVAC-Final 12/22/2023 Approved SCOTT FINNILA
Smoke Detectors 12/22/2023 Approved SCOTT FINNILA
Final 11/17/2025 Corrections Issued SCOTT FINNILA
Final 12/4/2025 OK to Issue CofO DAVID WILLIAMS