4936 N LOCKHAVEN AVE 90041
Certificate Information: 4936 N LOCKHAVEN AVE 90041
- Application / Permit
- 22014-20000-02681
- Plan Check / Job No.
- B22VN08479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) 1-STORY SFD W/BASEMENT AND ADD A 2ND STORY ADDITION (1046 SQFT) AND (115 SQFT TO 1ST FOOR), ENCLOSE (E) PORCH INTO PART OF THE BASEMENT (249 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Current Status
- CofO Issued on 12/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | PETER MOSESIAN |
| Corrections Issued | 7/2/2022 | PETER MOSESIAN |
| Quality Review Completed | 7/13/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| Plan Check Approved | 8/24/2022 | PETER MOSESIAN |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 12/4/2025 | DAVID WILLIAMS |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
| CofO Issued | 12/6/2025 | DEROLD HAUFF |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/19/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/19/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/19/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/19/2022 | CINDY QI |
| BHO/Hillside ordinance | Cleared | 7/19/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2022 | CINDY QI |
| Sewer availability | Cleared | 7/21/2022 | CINDY QI |
| Low Impact Development | Cleared | 8/4/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/8/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/17/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 12/7/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/7/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/13/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 12/20/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 1/3/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 1/12/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 2/21/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 2/21/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 2/21/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 2/21/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 3/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 3/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | CRAIG VAUGHAN |
| Deputy Wood Construction | 4/6/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/26/2023 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Inspection | CRAIG VAUGHAN |
| Gas Test | 4/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 4/26/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 4/26/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/26/2023 | Corrections Issued | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 4/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 4/26/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 5/5/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/5/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 5/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/12/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/16/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/22/2023 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 5/22/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/5/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/9/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 6/9/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 6/21/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 7/6/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/30/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Shower Pan | 8/30/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 11/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 11/8/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 11/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 11/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/17/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 11/17/2023 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 11/17/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 12/22/2023 | Approved | SCOTT FINNILA |
| Final | 12/22/2023 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/22/2023 | Approved | SCOTT FINNILA |
| Green Building Final | 12/22/2023 | Approved | SCOTT FINNILA |
| HVAC-Final | 12/22/2023 | Approved | SCOTT FINNILA |
| Smoke Detectors | 12/22/2023 | Approved | SCOTT FINNILA |
| Final | 11/17/2025 | Corrections Issued | SCOTT FINNILA |
| Final | 12/4/2025 | OK to Issue CofO | DAVID WILLIAMS |