5210 N BOTHWELL ROAD 91356

Certificate Information: 5210 N BOTHWELL ROAD 91356

Application / Permit
22014-20000-02680
Plan Check / Job No.
B22VN08476
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL WITH 2ND STORY ADDITION; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/15/2022
Issuing Office
Valley
Current Status
CofO in Progress on 10/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 SELLA BENYAMIN
Corrections Issued 6/27/2022 SELLA BENYAMIN
Quality Review Completed 6/29/2022 STEVEN KIM
Building Plans Picked Up 6/29/2022 APPLICANT
Applicant returned to address corrections 12/6/2022 SELLA BENYAMIN
Plan Check Approved 12/15/2022 SELLA BENYAMIN
Issued 12/15/2022 APPLICANT
CofO in Progress 8/15/2024 JOHN KIDWELL
No Progress 10/9/2025 SEAN WIRCH
CofO in Progress 10/9/2025 SEAN WIRCH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/30/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/30/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/30/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/5/2022 CARLOS AGUILERA
Low Impact Development Cleared 8/31/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 8/31/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/24/2022 GILBERT URREA
Private sewage disp. approval Cleared 12/12/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/17/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 2/23/2023 Corrections Issued DAVID SANDOVAL
Underground Mechanical 2/23/2023 Off-Hour Fees Due
Deputy Reinf. Concrete 4/11/2023 Conditional Approval DAVID SANDOVAL
Footing/Foundation/Slab 4/11/2023 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 4/14/2023 Conditional Approval DAVID SANDOVAL
Deputy Wood Construction 4/26/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Approved SEAN HAUPT
PLUMBING-Rough 5/30/2023 Approved SEAN WIRCH
BUILDING-Rough-Frame 6/5/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Partial Approval JOHN KIDWELL
Deputy Wood Construction 6/6/2023 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 6/12/2023 Approved SEAN HAUPT
HVAC-Rough 6/12/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 6/16/2023 Partial Approval JOHN KIDWELL
Shower Pan 6/16/2023 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 6/23/2023 Partial Approval SEAN HAUPT
Green Building Rough 6/23/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 6/23/2023 Approved SEAN HAUPT
Verify Sprinkler Sign Off 6/23/2023 Approved SEAN HAUPT
Insulation 6/30/2023 Approved SEAN HAUPT
Drywall Nailing 7/11/2023 Approved SEAN HAUPT
ELECTRICAL-Final 2/20/2024 Approved JOHN KIDWELL
Service/Power Release 2/20/2024 Partial Inspection JOHN KIDWELL
HVAC-Final 2/26/2024 Approved JOHN KIDWELL
PLUMBING-Final 2/26/2024 Approved JOHN KIDWELL
Service/Power Release 3/6/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/5/2024 Approved JOHN KIDWELL
Final 8/5/2024 Corrections Issued JOHN KIDWELL
Green Building Final 8/5/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Approved JOHN KIDWELL
Smoke Detectors 8/5/2024 Approved JOHN KIDWELL
Final 8/9/2024 OK to Issue CofO JOHN KIDWELL
Special/Order Compliance 3/4/2025 Corrections Issued JOHN KIDWELL