7120 N LASAINE AVE 91406
Certificate Information: 7120 N LASAINE AVE 91406
- Application / Permit
- 22014-20000-02661
- Plan Check / Job No.
- B22VN08398
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT EX. DETACHED STORAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | ROSENDO MEDINA |
| Corrections Issued | 6/4/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 6/8/2022 | APPLICANT |
| Applicant returned to address corrections | 7/6/2022 | ZAW HAN |
| Plan Check Approved | 7/11/2022 | ZAW HAN |
| Issued | 5/30/2023 | APPLICANT |
| CofO in Progress | 6/12/2024 | JON MCHUGH |
| CofO Issued | 6/20/2024 | JOHN JANSON |
| Permit Finaled | 6/20/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/10/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/13/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/13/2022 | MEGAN GODINEZ |
Contact Information
| Architect | Asamoah,, B Kwesi; Lic. No.: C36558 | 850 ROSE AVENUE VENICE, CA 90291 |
| Contractor | Mod Design Build; Lic. No.: 1031321-B | PO BOX 65008 LOS ANGELES, CA 90065 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/12/2023 | Conditional Approval | JON MCHUGH |
| ELECTRICAL-Rough | 7/7/2023 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 7/7/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 7/7/2023 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 7/7/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 11/2/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 11/2/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 11/2/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 11/2/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 11/2/2023 | Corrections Issued | JON MCHUGH |
| Sewer | 11/2/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 11/20/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 11/20/2023 | Not Ready for Inspection | JON MCHUGH |
| Sewer | 11/20/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 11/29/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 11/29/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | JON MCHUGH |
| Green Building Rough | 11/29/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 11/29/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 11/29/2023 | Not Ready for Inspection | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 11/29/2023 | Corrections Issued | JON MCHUGH |
| Shower Pan | 11/29/2023 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 12/4/2023 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 12/4/2023 | Corrections Issued | MORRIS JACKSON |
| Shower Pan | 12/4/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 12/7/2023 | Approved | JON MCHUGH |
| Green Building Rough | 12/7/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 12/7/2023 | Approved | JON MCHUGH |
| Insulation | 12/7/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 12/7/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 12/15/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 4/24/2024 | Corrections Issued | JON MCHUGH |
| Final | 4/24/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/24/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 4/24/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 4/24/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 4/24/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 6/4/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 6/4/2024 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 6/4/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 6/4/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 6/4/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | JON MCHUGH |
| ELECTRICAL-Final | 6/11/2024 | Approved | JON MCHUGH |
| Final | 6/11/2024 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 6/11/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 6/11/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Approved | JON MCHUGH |