7120 N LASAINE AVE 91406

Certificate Information: 7120 N LASAINE AVE 91406

Application / Permit
22014-20000-02661
Plan Check / Job No.
B22VN08398
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT EX. DETACHED STORAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 5/30/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 ROSENDO MEDINA
Corrections Issued 6/4/2022 ROSENDO MEDINA
Building Plans Picked Up 6/8/2022 APPLICANT
Applicant returned to address corrections 7/6/2022 ZAW HAN
Plan Check Approved 7/11/2022 ZAW HAN
Issued 5/30/2023 APPLICANT
CofO in Progress 6/12/2024 JON MCHUGH
CofO Issued 6/20/2024 JOHN JANSON
Permit Finaled 6/20/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/10/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/10/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/13/2022 MEGAN GODINEZ
Sewer availability Cleared 6/13/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/13/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/13/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/13/2022 MEGAN GODINEZ

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Contractor Mod Design Build; Lic. No.: 1031321-B PO BOX 65008      LOS ANGELES, CA 90065

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/12/2023 Conditional Approval JON MCHUGH
ELECTRICAL-Rough 7/7/2023 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 7/7/2023 Approved JON MCHUGH
HVAC-Rough 7/7/2023 Not Ready for Inspection JON MCHUGH
Underground Mechanical 7/7/2023 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 11/2/2023 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 11/2/2023 Not Ready for Inspection JON MCHUGH
Green Building Rough 11/2/2023 Not Ready for Inspection JON MCHUGH
HVAC-Rough 11/2/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 11/2/2023 Corrections Issued JON MCHUGH
Sewer 11/2/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Partial Approval JON MCHUGH
HVAC-Rough 11/20/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 11/20/2023 Not Ready for Inspection JON MCHUGH
Sewer 11/20/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 11/29/2023 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 11/29/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Approved JON MCHUGH
Green Building Rough 11/29/2023 Not Ready for Inspection JON MCHUGH
HVAC-Rough 11/29/2023 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 11/29/2023 Not Ready for Inspection JON MCHUGH
Rough-Elec/Plmb/HVAC 11/29/2023 Corrections Issued JON MCHUGH
Shower Pan 11/29/2023 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 12/4/2023 Partial Approval MORRIS JACKSON
PLUMBING-Rough 12/4/2023 Corrections Issued MORRIS JACKSON
Shower Pan 12/4/2023 Approved MORRIS JACKSON
BUILDING-Rough-Frame 12/7/2023 Approved JON MCHUGH
ELECTRICAL-Rough 12/7/2023 Approved JON MCHUGH
Green Building Rough 12/7/2023 Approved JON MCHUGH
HVAC-Rough 12/7/2023 Approved JON MCHUGH
Insulation 12/7/2023 Corrections Issued JON MCHUGH
PLUMBING-Rough 12/7/2023 Approved JON MCHUGH
Drywall Nailing 12/15/2023 Approved JON MCHUGH
ELECTRICAL-Final 4/24/2024 Corrections Issued JON MCHUGH
Final 4/24/2024 Corrections Issued JON MCHUGH
Green Building Final 4/24/2024 Not Ready for Inspection JON MCHUGH
HVAC-Final 4/24/2024 Corrections Issued JON MCHUGH
PLUMBING-Final 4/24/2024 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Not Ready JON MCHUGH
Smoke Detectors 4/24/2024 Approved JON MCHUGH
ELECTRICAL-Final 6/4/2024 Not Ready for Inspection JON MCHUGH
Final 6/4/2024 Not Ready for Inspection JON MCHUGH
Green Building Final 6/4/2024 Not Ready for Inspection JON MCHUGH
HVAC-Final 6/4/2024 Approved JON MCHUGH
PLUMBING-Final 6/4/2024 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Not Ready JON MCHUGH
ELECTRICAL-Final 6/11/2024 Approved JON MCHUGH
Final 6/11/2024 OK to Issue CofO JON MCHUGH
Green Building Final 6/11/2024 Approved JON MCHUGH
PLUMBING-Final 6/11/2024 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Approved JON MCHUGH