8149 N GENESTA AVE 91406
Certificate Information: 8149 N GENESTA AVE 91406
- Application / Permit
- 22014-20000-02638
- Plan Check / Job No.
- B22VN08377
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION INTO AN ACCESSORY DWELLING UNIT. NEW SECOND STORY ADDITION.
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Current Status
- CofO Issued on 10/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2022 | KEVIN MORALES |
| Corrections Issued | 6/13/2022 | KEVIN MORALES |
| Quality Review Completed | 6/15/2022 | EUGENE BARBEAU |
| Plan Check Approved | 8/9/2022 | KEVIN MORALES |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 8/23/2023 | RAUL OLAGI |
| Permit Finaled | 10/17/2023 | RUBEN SALAS |
| CofO Issued | 10/17/2023 | RUBEN SALAS |
| Permit Finaled | 10/17/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/22/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 8/1/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 8/2/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/20/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 1/23/2023 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 1/30/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/28/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 3/28/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 3/28/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/28/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 3/28/2023 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/21/2023 | Partial Approval | RAUL OLAGI |
| Insulation | 4/26/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/26/2023 | Not Ready for Inspection | RAUL OLAGI |
| Drywall Nailing | 5/5/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 5/5/2023 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 7/19/2023 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/11/2023 | Approved | RAUL OLAGI |
| Final | 8/11/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 8/11/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 8/11/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 8/11/2023 | Approved | RAUL OLAGI |
| Final | 8/23/2023 | OK to Issue CofO | RAUL OLAGI |