14665 W BRAND BLVD 91345

Certificate Information: 14665 W BRAND BLVD 91345

Application / Permit
22014-20000-02634
Plan Check / Job No.
B22VN08339
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 24' X 27' DETACHED GARAGE AND ADD 21'-9" X 28' 2-STORY TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 RAPHAEL ROSAS
Corrections Issued 6/29/2022 RAPHAEL ROSAS
Quality Review Completed 7/1/2022 STEVEN KIM
Building Plans Picked Up 7/1/2022 APPLICANT
Applicant returned to address corrections 9/13/2022 RAPHAEL ROSAS
Plan Check Approved 9/21/2022 RAPHAEL ROSAS
Issued 9/27/2022 APPLICANT
CofO in Progress 9/6/2023 JENNIFER RABUCHIN
Permit Finaled 11/14/2023 RUBEN SALAS
CofO Issued 11/14/2023 RUBEN SALAS
Permit Finaled 11/14/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/8/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/8/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/8/2022 COLIN LOREDO
Sewer availability Cleared 8/8/2022 COLIN LOREDO
Construction near power lines Cleared 8/26/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2022 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 1/9/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 2/23/2023 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/17/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 4/17/2023 Approved JENNIFER RABUCHIN
Wood Frame 5/3/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Corrections Issued ROBERT GOLD
PLUMBING-Rough 6/8/2023 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 6/13/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/13/2023 Corrections Issued JENNIFER RABUCHIN
Gas Test 6/13/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/13/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/20/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/20/2023 Approved JENNIFER RABUCHIN
Green Building Rough 6/20/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 6/20/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/20/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/20/2023 Approved JENNIFER RABUCHIN
Insulation 6/23/2023 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 6/29/2023 Partial Approval JENNIFER RABUCHIN
Insulation 6/29/2023 Approved JENNIFER RABUCHIN
Shower Pan 6/29/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 7/12/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/12/2023 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/24/2023 Approved JENNIFER RABUCHIN
Reinforced Masonry Frame 7/28/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Final 8/16/2023 Corrections Issued ROBERT GOLD
Green Building Final 8/16/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Final 8/16/2023 Corrections Issued ROBERT GOLD
PLUMBING-Final 8/16/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 8/24/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/24/2023 Corrections Issued JENNIFER RABUCHIN
Final 8/24/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/24/2023 Approved JENNIFER RABUCHIN
HVAC-Final 8/24/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 8/24/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 8/24/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/24/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 8/24/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 8/24/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/29/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/6/2023 Partial Approval JENNIFER RABUCHIN
Final 9/6/2023 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 9/6/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Approved JENNIFER RABUCHIN