10909 N NESTLE AVE 91326

Certificate Information: 10909 N NESTLE AVE 91326

Application / Permit
22014-20000-02633
Plan Check / Job No.
B22VN08338
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'-4" X 11'-6" ADDITION TO SFD AND (N) 18'-10" X 11'-5" ATTACHED PATIO COVER.
Permit Issued
Issued on 1/9/2023
Issuing Office
Current Status
CofO Issued on 5/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 SERGIO MUNIZ
Corrections Issued 6/2/2022 SERGIO MUNIZ
Plan Check Approved 6/29/2022 SERGIO MUNIZ
Building Plans Picked Up 6/30/2022 APPLICANT
Issued 1/9/2023 APPLICANT
CofO in Progress 5/9/2023 JOHN KIDWELL
Permit Finaled 5/11/2023 MICHAEL SMITH
CofO Issued 5/11/2023 MICHAEL SMITH
Permit Finaled 5/11/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/15/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/15/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/3/2023 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 3/3/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 3/3/2023 Approved DAVID SCANTLIN
Pre-Inspection 3/3/2023 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/29/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 3/29/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Approved DAVID SCANTLIN
HVAC-Rough 3/29/2023 Approved DAVID SCANTLIN
Drywall Nailing 4/4/2023 Approved DAVID SCANTLIN
Insulation 4/4/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/4/2023 Approved DAVID SCANTLIN
Deputy Wood Construction 4/17/2023 Conditional Approval DAVID SCANTLIN
Deputy Wood Construction 4/17/2023 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 5/3/2023 Approved DAVID SCANTLIN
Final 5/3/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 5/3/2023 Approved DAVID SCANTLIN
Green Building Rough 5/3/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 5/3/2023 Approved DAVID SCANTLIN
Final 5/8/2023 OK to Issue CofO JOHN KIDWELL