3864 N RHODES AVE 91604
Certificate Information: 3864 N RHODES AVE 91604
- Application / Permit
- 22014-20000-02632
- Plan Check / Job No.
- B22VN08337
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 700 SF ADDITION TO 2ND STORY ABOVE THE (E) ATTACHED GARAGE FOR (E) 2 STORY SFD
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2022 | PETER MOSESIAN |
| Corrections Issued | 6/26/2022 | PETER MOSESIAN |
| Quality Review Completed | 7/8/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Plan Check Approved | 1/11/2023 | PETER MOSESIAN |
| Issued | 5/16/2023 | APPLICANT |
| CofO in Progress | 10/27/2025 | CHRISTOPHE COCHRAN |
| CofO in Progress | 10/28/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
| CofO Issued | 1/2/2026 | RUBEN SALAS |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/2/2022 | VASIL MIHALEV |
| Address approval | Cleared | 12/21/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | COLIN LOREDO |
| BHO/Hillside ordinance | Cleared | 12/21/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/27/2022 | COLIN LOREDO |
| Low Impact Development | Cleared | 12/30/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/30/2022 | LEE GUILBEAUX |
Contact Information
| Architect | Abrahams,, Bob; Lic. No.: C30213 | 731 INDIANA AVENUE VENICE, CA 90291 |
| Contractor | Perez Construction & Development Corporation; Lic. No.: 771304-B | 1521 S COCHRAN AVE LOS ANGELES, CA 90019 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 8/10/2023 | Conditional Approval | JUAN VALENZUELA |
| Structural Steel Frame | 8/22/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 8/23/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 8/31/2023 | Approved | CHRISTOPHE COCHRAN |
| Light Gage Steel Frame | 9/1/2023 | Approved | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 9/1/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 9/8/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/17/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2023 | Conditional Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/8/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Gas Test | 1/8/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/8/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/8/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/12/2024 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 1/12/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/19/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Gas Test | 1/19/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 1/19/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/16/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/26/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 2/26/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 2/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 2/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/11/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 5/9/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 9/25/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 9/25/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 9/25/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/10/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 9/10/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 9/10/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 9/10/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/6/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 10/6/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/28/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |