303 N CITRUS AVE 90036

Certificate Information: 303 N CITRUS AVE 90036

Application / Permit
22014-20000-02619
Plan Check / Job No.
B22VN08282
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE (384 SQFT) INTO ADU W/ 1ST (196 SQFT) AND 2ND FLOOR (427 SQFT) PER LAMC 12.22A.33 (c)(d)
Permit Issued
Issued on 10/12/2023
Issuing Office
Valley
Current Status
Issued on 10/12/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 6/23/2022 PETER MOSESIAN
Corrections Issued 6/25/2022 PETER MOSESIAN
Quality Review Completed 6/30/2022 OMID HEDAYAT
Building Plans Picked Up 7/1/2022 APPLICANT
Applicant returned to address corrections 3/29/2023 PETER MOSESIAN
Plan Check Approved 10/12/2023 PETER MOSESIAN
Issued 10/12/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/23/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/26/2022 STEVE MELGAR
Sewer availability Cleared 7/26/2022 STEVE MELGAR
Construction near power lines Cleared 10/7/2022 RIDWAN HARDY
Low Impact Development Cleared 2/21/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/12/2023 AMBER CAMPBELL

Contact Information

Contractor L E Construction & Development Inc; Lic. No.: 1051866-B 7111 SANTA MONICA BLVD   SUITE B-272    LOS ANGELES, CA 90046
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

CRAIG DAVIS, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
AMIR NAZARIAN, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
GEM DE OCAMPO, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
DEVON JACKSON, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
JOSH MEISTER, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
ANTHONY RAMOS, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
KELVIN MARTINEZ, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER MORFIN, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MAGCALAS, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
ALEX COLIN, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT FINNILA, (213) 216-1123 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/13/2023 Conditional Approval RICHARD DOCKUS
Deputy Drilled-In Anchors 10/16/2023 Conditional Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 10/17/2023 Corrections Issued RICHARD DOCKUS
Underground Mechanical 11/1/2023 No Access for Inspection RICHARD DOCKUS
Special/Order Compliance 11/2/2023 Corrections Issued DAVID FEILER
Underground Mechanical 11/14/2023 Off-Hour Fees Due
Footing/Foundation/Slab 12/26/2023 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 12/28/2023 Not Ready for Inspection RICHARD DOCKUS
Special/Order Compliance 1/3/2024 Partial Inspection JOAQUIN GREENOUGH
Special/Order Compliance 1/31/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Special/Order Compliance 2/1/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/13/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 2/13/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 2/13/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Pre-Inspection 2/13/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/29/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 2/29/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 2/29/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 2/29/2024 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 2/29/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 2/29/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/4/2024 Corrections Issued JOAQUIN GREENOUGH
METHANE-Barrier 3/4/2024 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 3/4/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/1/2024 Conditional Approval AMIR NAZARIAN
METHANE-Barrier 4/1/2024 Conditional Approval AMIR NAZARIAN
METHANE-Subgrade 4/1/2024 Conditional Approval AMIR NAZARIAN
Underground Mechanical 4/1/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 4/2/2024 Not Ready for Inspection AMIR NAZARIAN
PLUMBING-Rough 4/2/2024 Not Ready for Inspection AMIR NAZARIAN
Underground Mechanical 4/2/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 4/11/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 4/11/2024 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 4/11/2024 Corrections Issued RONNIE MINDANAO
Special/Order Compliance 4/11/2024 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/22/2024 Not Ready for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 4/22/2024 Approved RONNIE MINDANAO
METHANE-Barrier 4/22/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 4/22/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 4/22/2024 Partial Approval RONNIE MINDANAO
BUILDING-Rough-Frame 5/2/2024 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 5/2/2024 Approved JOAQUIN GREENOUGH
Green Building Rough 5/2/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 5/2/2024 Corrections Issued JOAQUIN GREENOUGH
METHANE-Rough 5/2/2024 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/2/2024 Corrections Issued JOAQUIN GREENOUGH
Wood Frame 5/2/2024 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 5/6/2024 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/6/2024 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/7/2024 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 5/7/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 5/7/2024 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/22/2024 Not Ready for Inspection AMIR NAZARIAN
Green Building Rough 5/22/2024 Not Ready for Inspection AMIR NAZARIAN
Insulation 5/22/2024 Conditional Approval AMIR NAZARIAN
Interior/Exterior Lathing 5/22/2024 Not Ready for Inspection AMIR NAZARIAN
Shower Pan 5/22/2024 Not Ready for Inspection AMIR NAZARIAN
Wood Frame 5/22/2024 Not Ready for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 5/28/2024 Approved ENRIQUE MIRELES
Drywall Nailing 5/28/2024 Approved ENRIQUE MIRELES
Green Building Rough 5/28/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/28/2024 Approved ENRIQUE MIRELES
Shower Pan 5/28/2024 Approved ENRIQUE MIRELES