15045 W WYANDOTTE ST 91405

Certificate Information: 15045 W WYANDOTTE ST 91405

Application / Permit
22014-20000-02618
Plan Check / Job No.
B22VN08279
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING AND ADDTION OF ATTACHED 20'-0" X 19'-6" GARAGE - ALL WORK PER ENGINEER
Permit Issued
Issued on 11/30/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 DANIEL ABRAMYAN
Corrections Issued 6/18/2022 DANIEL ABRAMYAN
Building Plans Picked Up 6/23/2022 APPLICANT
Issued 11/30/2022 APPLICANT
CofO in Progress 8/8/2023 GREGG CUMMINGS
Permit Finaled 9/11/2023 RUBEN SALAS
CofO Issued 9/11/2023 RUBEN SALAS
Permit Finaled 9/11/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/6/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 10/6/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 11/14/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 11/15/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/6/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/23/2023 Partial Approval MATTHEW NELSON
PLUMBING-Rough 2/23/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/26/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 4/26/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/26/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/2/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 5/2/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/2/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/8/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 5/8/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/8/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 5/11/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/22/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 5/26/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/5/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 6/5/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 6/7/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 7/11/2023 Not Ready for Inspection ROBERT GOLD
Final 7/11/2023 Corrections Issued ROBERT GOLD
Green Building Final 7/11/2023 Approved ROBERT GOLD
HVAC-Final 7/11/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Final 7/11/2023 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 7/11/2023 Approved ROBERT GOLD
ELECTRICAL-Final 7/28/2023 Not Ready for Inspection GREGG CUMMINGS
Final 7/28/2023 Corrections Issued GREGG CUMMINGS
HVAC-Final 7/28/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Approved GREGG CUMMINGS
ELECTRICAL-Final 8/7/2023 Approved GREGG CUMMINGS
Final 8/7/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 8/7/2023 Approved GREGG CUMMINGS
PLUMBING-Final 8/7/2023 Approved GREGG CUMMINGS