13039 N GARRIS AVE 91344

Certificate Information: 13039 N GARRIS AVE 91344

Application / Permit
22014-20000-02605
Plan Check / Job No.
B22VN08227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Convert a portion of the (E) Covered Patio with addition to a living room and Interior Remodel of 1st floor of (E) 2-story SFD
Permit Issued
Issued on 8/3/2022
Issuing Office
Current Status
Issued on 8/3/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/8/2022 APPLICANT
Assigned to Plan Check Engineer 6/14/2022 MINA HABILI
Corrections Issued 6/15/2022 MINA HABILI
Applicant returned to address corrections 7/21/2022 MINA HABILI
Plan Check Approved 7/28/2022 MINA HABILI
Issued 8/3/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/6/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 7/6/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 7/6/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 7/6/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 7/6/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 7/28/2022 KIRK LINKLATER
Hold Cleared 9/21/2022 PRISCILLA RUIZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: NA93320       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2022 Approved DAVID SCANTLIN
METHANE-Barrier 8/12/2022 Approved DAVID SCANTLIN
METHANE-Subgrade 8/12/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 8/12/2022 Approved DAVID SCANTLIN
Pre-Inspection 8/12/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/28/2022 Approved DAVID SCANTLIN
Final 11/28/2022 Corrections Issued DAVID SCANTLIN
METHANE-Final 11/28/2022 Approved DAVID SCANTLIN
METHANE-Rough 11/28/2022 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 11/28/2022 Approved DAVID SCANTLIN
Final 7/18/2023 Not Ready for Inspection DAVID SCANTLIN