20233 W CHASE ST 91306
Certificate Information: 20233 W CHASE ST 91306
- Application / Permit
- 22014-20000-02604
- Plan Check / Job No.
- B22VN08226
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan PROPOSED SINGLE FAMILY DWELLING UNIT PER SB9 TWO-UNIT DEVELOPMENT CA GOVT CODE 65852.21. 1 OF 2
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | NGHI SU |
| Corrections Issued | 7/1/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 7/7/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/27/2022 | NGHI SU |
| Plan Check Approved | 11/3/2022 | NGHI SU |
| Issued | 11/3/2022 | APPLICANT |
| CofO in Progress | 7/17/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/19/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/3/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/5/2022 | CHRIS CHAHBAZ |
| Hydrant and Access approval | Cleared | 10/22/2022 | RUEL COLE |
| Senate Bill 9 | Cleared | 10/31/2022 | CLAUDE GOODING |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: NA35492 | , |
| Contractor | Owner-Builder | , |
| Engineer | Van, Elden, Alexander Craig; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/14/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/1/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 12/1/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/23/2023 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/23/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/23/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/23/2023 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 1/23/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 1/23/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 2/8/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/8/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Shower Pan | 2/8/2023 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 2/8/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 2/13/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/13/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/21/2023 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 2/21/2023 | Approved | CHRIS CHRISTENSEN |
| Sewer | 2/21/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/5/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/5/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/8/2023 | Approved | JOHN KIDWELL |
| HVAC-Final | 6/8/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 6/14/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 6/14/2023 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/14/2023 | Approved | CHRIS CHRISTENSEN |