12334 W LA MAIDA ST 91607

Certificate Information: 12334 W LA MAIDA ST 91607

Application / Permit
22014-20000-02603
Plan Check / Job No.
B22VN08225
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. GROUND FLOOR ADDITION TO FRONT AND REAR OF (E) SFD
Permit Issued
Issued on 12/28/2022
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 FARSHAD ALIMOHAMADI
Corrections Issued 5/26/2022 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/9/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 7/13/2022 FARSHAD ALIMOHAMADI
Issued 12/28/2022 APPLICANT
CofO in Progress 9/5/2023 KIRK SANDERS
Permit Finaled 1/17/2024 RUBEN SALAS
CofO Issued 1/17/2024 RUBEN SALAS
Permit Finaled 1/17/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/25/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/28/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/28/2022 DAGOVERTO GUERRERO
Specific Plan Cleared 7/11/2022 CORREY KITCHENS

Contact Information

Architect Wiener,, Morgan G D; Lic. No.: NA30929       ,
Contractor B & L Ruiz Builders Inc; Lic. No.: 947603-B       ,
Engineer Vasquez,, Mario Alberto; Lic. No.: C89006 43023 40TH ST WEST      LANCASTER, CA 93536

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/15/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/23/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 3/8/2023 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Partial Approval THOMAS FINNILA
Deputy Wood Construction 4/17/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/9/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 5/9/2023 Approved KIRK SANDERS
HVAC-Rough 5/9/2023 Corrections Issued KIRK SANDERS
MERV13>=Rough 5/9/2023 Approved KIRK SANDERS
PLUMBING-Rough 5/9/2023 Approved KIRK SANDERS
HVAC-Rough 5/12/2023 Off-Hour Fees Due
BUILDING-Rough-Frame 5/16/2023 Approved KIRK SANDERS
HVAC-Rough 5/16/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 6/6/2023 Off-Hour Fees Due
Interior/Exterior Lathing 6/6/2023 Partial Approval JUAN VALENZUELA
Shower Pan 6/6/2023 Approved JUAN VALENZUELA
Shower Pan 6/6/2023 Off-Hour Fees Due
Insulation 6/9/2023 Approved JUAN VALENZUELA
Drywall Nailing 6/15/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 6/16/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/16/2023 Off-Hour Fees Due
ELECTRICAL-Final 8/17/2023 Approved KIRK SANDERS
Final 8/17/2023 Corrections Issued KIRK SANDERS
HVAC-Final 8/17/2023 Partial Approval KIRK SANDERS
PLUMBING-Final 8/17/2023 Corrections Issued KIRK SANDERS
Final 9/1/2023 OK to Issue CofO KIRK SANDERS
Footing/Foundation/Slab 9/1/2023 Approved KIRK SANDERS
HVAC-Final 9/1/2023 Approved KIRK SANDERS
MERV13>=Final 9/1/2023 Approved KIRK SANDERS
PLUMBING-Final 9/1/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 9/1/2023 Approved KIRK SANDERS