5666 E HUB ST 90042

Certificate Information: 5666 E HUB ST 90042

Application / Permit
22014-20000-02598
Plan Check / Job No.
B22VN08211
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED IRREGULAR SHAPED ADDITION TO SFD.
Permit Issued
Issued on 8/22/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 HAYATO TSUCHIYA
Corrections Issued 6/18/2022 HAYATO TSUCHIYA
Building Plans Picked Up 6/22/2022 APPLICANT
Plan Check Approved 8/22/2023 SERGIO MUNIZ
Issued 8/22/2023 APPLICANT
CofO in Progress 3/29/2024 ALIZAH MAYAGOITIA
Permit Finaled 5/17/2024 DEROLD HAUFF
CofO Issued 5/17/2024 DEROLD HAUFF
Permit Finaled 5/17/2024 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 7/20/2022 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 7/20/2022 TREVOR QUAN
Grading Pre-Inspection Cleared 7/21/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 8/1/2022 TREVOR QUAN
Sewer availability Cleared 8/1/2022 TREVOR QUAN
HPOZ Cleared 8/9/2023 MICAELA TORRES-GIL
ZI Cleared 8/9/2023 MICAELA TORRES-GIL

Contact Information

Contractor California Skyline Remodeling Inc; Lic. No.: 879490-B 21243 VENTURA BLVD STE 227      WOODLAND HILLS, CA 91364
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/29/2023 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 12/4/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 12/13/2023 Partial Approval ROY SPAULDING
Green Building Rough 12/13/2023 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 12/13/2023 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 12/21/2023 Partial Approval ROY SPAULDING
Green Building Rough 12/21/2023 Not Ready for Inspection ROY SPAULDING
Deputy Wood Construction 1/10/2024 Conditional Approval ROY SPAULDING
BUILDING-Rough-Frame 1/16/2024 Corrections Issued CRAIG VAUGHAN
Green Building Rough 1/16/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 1/16/2024 Approved CRAIG VAUGHAN
Wood Frame 1/16/2024 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 1/24/2024 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 1/24/2024 Approved ROY SPAULDING
Green Building Rough 1/24/2024 Partial Approval ROY SPAULDING
HVAC-Rough 1/24/2024 Corrections Issued ROY SPAULDING
PLUMBING-Rough 1/24/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 1/29/2024 Approved ROY SPAULDING
Wood Frame 1/29/2024 Approved ROY SPAULDING
Insulation 2/1/2024 Approved ROY SPAULDING
Drywall Nailing 2/7/2024 Partial Approval JOSH MEISTER
Green Building Rough 2/7/2024 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 2/7/2024 Approved JOSH MEISTER
Shower Pan 2/7/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 3/20/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 3/20/2024 Approved ALIZAH MAYAGOITIA
Final 3/20/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 3/20/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/20/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 3/20/2024 Approved ALIZAH MAYAGOITIA
Final 3/26/2024 Conditional Approval ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Approved ALIZAH MAYAGOITIA
Final 3/28/2024 OK to Issue CofO ALIZAH MAYAGOITIA