7309 N WILBUR AVE 91335
Certificate Information: 7309 N WILBUR AVE 91335
- Application / Permit
- 22014-20000-02597
- Plan Check / Job No.
- B22VN08208
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-10" X 18'-4" ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 9/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 5/30/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/6/2022 | APPLICANT |
| Plan Check Approved | 9/13/2022 | ZAW HAN |
| Issued | 9/14/2022 | APPLICANT |
| CofO in Progress | 8/16/2024 | JEFFREY BULL |
| CofO Issued | 9/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/7/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/8/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
Contact Information
| No Data Available. |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/29/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 11/29/2022 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Rough | 11/29/2022 | Partial Approval | SEAN WIRCH |
| Sewer | 11/29/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2023 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 4/13/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 4/13/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 4/13/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 4/13/2023 | Not Ready for Inspection | JEFFREY BULL |
| Wood Frame | 4/13/2023 | Not Ready for Inspection | JEFFREY BULL |
| Pre-Inspection | 1/19/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 2/9/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 2/9/2024 | Approved | JEFFREY BULL |
| Insulation | 2/9/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 2/9/2024 | Approved | JEFFREY BULL |
| Sewer | 2/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| Deputy Wood Construction | 2/15/2024 | Conditional Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 2/23/2024 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 2/28/2024 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 2/28/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 3/12/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 3/18/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 3/18/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 7/19/2024 | Approved | JEFFREY BULL |
| Final | 7/19/2024 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 7/19/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 7/19/2024 | Not Ready for Inspection | JEFFREY BULL |
| Final | 7/30/2024 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 7/30/2024 | Approved | JEFFREY BULL |
| Final | 8/16/2024 | OK to Issue CofO | JEFFREY BULL |