1772 S ORANGE GROVE AVE 90019
Certificate Information: 1772 S ORANGE GROVE AVE 90019
- Application / Permit
- 22014-20000-02596
- Plan Check / Job No.
- B22VN08201
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 20'-9" x 25'-0" TO (E) S.F.D. PER ENGINEERING
- Permit Issued
- Issued on 7/20/2022
- Issuing Office
- Current Status
- CofO Issued on 6/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | ALFRED RAMIREZ |
| Corrections Issued | 5/31/2022 | ALFRED RAMIREZ |
| Plan Check Approved | 7/19/2022 | ALEC MOUSAKHANIAN |
| Issued | 7/20/2022 | APPLICANT |
| Building Plans Picked Up | 7/20/2022 | APPLICANT |
| CofO in Progress | 6/5/2023 | JOSE AVILA |
| Permit Finaled | 6/11/2023 | DEROLD HAUFF |
| CofO Issued | 6/11/2023 | DEROLD HAUFF |
| Permit Finaled | 6/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/3/2022 | CELINA MORENO |
| Sewer availability | Cleared | 6/3/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2022 | JEANETTE VONG |
| Public Works-Highway Ded. | Cleared | 5/29/2023 | ADRIAN SANCHEZ |
| Public Works-Open Permits | Cleared | 5/29/2023 | ADRIAN SANCHEZ |
| Public Works-Sewers | Cleared | 5/29/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
| Engineer | Ehat,, Frederick P; Lic. No.: C30383 | 34 OPHIR DR DURANGO, CO 81301 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/6/2022 | Conditional Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 9/22/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Approved | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 10/31/2022 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 11/7/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 11/7/2022 | Approved | JOSE AVILA |
| Shower Pan | 11/21/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/28/2022 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 12/1/2022 | No Access for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 12/5/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/5/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 12/5/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 12/7/2022 | Approved | JOSE AVILA |
| Insulation | 12/7/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/7/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 12/12/2022 | Approved | BRENDAN MORELLI |
| Green Building Rough | 12/12/2022 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/27/2023 | Approved | JOSE AVILA |
| Shower Pan | 1/27/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 2/1/2023 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 2/1/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 2/1/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 2/1/2023 | Approved | JOSE AVILA |
| Final | 6/5/2023 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 6/5/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 6/5/2023 | Approved | JOSE AVILA |