818 N RADCLIFFE AVE 90272
Certificate Information: 818 N RADCLIFFE AVE 90272
- Application / Permit
- 22014-20000-02544
- Plan Check / Job No.
- B22VN08050
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 2' 10" X 6' 1" & 3' 11" X 1' 5" TO (E) SFD AND REMODEL TO REVISE 1ST FLOOR PLAN LAYOUT AND REMODEL 2ND FLOOR BATHROOM. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 6/5/2022 | GURUNATH NESARAJAH |
| Quality Review Completed | 6/8/2022 | OMID HEDAYAT |
| Plan Check Approved | 9/7/2022 | GURUNATH NESARAJAH |
| Issued | 5/12/2023 | APPLICANT |
| CofO in Progress | 1/18/2024 | EVAN COOPER |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
| CofO Issued | 4/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/23/2022 | JENSON LEE |
| ZI | Cleared | 6/23/2022 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 9/7/2022 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Smith Pacific Construction Inc; Lic. No.: 1018523-B | 1515 7TH STREET #325 SANTA MONICA, CA 90401 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 7/6/2023 | Partial Approval | KENNETH NAGLE |
| Insulation | 7/6/2023 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/3/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/16/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/16/2023 | Corrections Issued | ARAM AVEDISIAN |
| Shower Pan | 8/21/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/25/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 9/1/2023 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 9/1/2023 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 9/18/2023 | Corrections Issued | EVAN COOPER |
| Insulation | 10/3/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/3/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 10/11/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 1/17/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 1/17/2024 | Approved | EVAN COOPER |
| Final | 1/17/2024 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/17/2024 | Approved | EVAN COOPER |
| Green Building Final | 1/17/2024 | Approved | EVAN COOPER |
| Green Building Rough | 1/17/2024 | Approved | EVAN COOPER |
| HVAC-Final | 1/17/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/17/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/17/2024 | Approved | EVAN COOPER |
| Final | 1/18/2024 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 1/18/2024 | Approved | EVAN COOPER |