22333 W HART ST 91303
Certificate Information: 22333 W HART ST 91303
- Application / Permit
- 22014-20000-02543
- Plan Check / Job No.
- B22VN08048
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20'-4" X 48'-6" IRREG SHAPED ADDITION AND REMODEL TO SFD FOR TWO NEW BEDROOM AND TWO NEW BATHROOMS PER ENGINEER
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 6/1/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 7/29/2022 | ALFRED RAMIREZ |
| Building Plans Picked Up | 7/29/2022 | APPLICANT |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 11/30/2023 | MORRIS JACKSON |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
| CofO Issued | 12/27/2023 | JOHN JANSON |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/6/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 7/26/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/26/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chapman,, Joseph; Lic. No.: S6141 | 440 E CORPORATE DR STE 103 MERIDIAN, ID 83642 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 9/9/2022 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 9/9/2022 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 9/13/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/30/2023 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/25/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/25/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 4/25/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/25/2023 | Approved | TROY SANDERS |
| Green Building Rough | 5/4/2023 | Approved | TROY SANDERS |
| Insulation | 5/4/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/4/2023 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 5/10/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/22/2023 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Final | 11/28/2023 | Approved | MORRIS JACKSON |
| Final | 11/28/2023 | OK to Issue CofO | MORRIS JACKSON |
| Green Building Final | 11/28/2023 | Approved | MORRIS JACKSON |
| HVAC-Final | 11/28/2023 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 11/28/2023 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 11/28/2023 | Approved | MORRIS JACKSON |