11462 N RUGGIERO AVE 91342

Certificate Information: 11462 N RUGGIERO AVE 91342

Application / Permit
22014-20000-02539
Plan Check / Job No.
B22VN08032
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
14'-3" X 19'-2" ADDITION TO AND CONVERT THE (E) DET. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/9/2023
Issuing Office
Valley
Current Status
Issued on 3/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/30/2022 APPLICANT
Assigned to Plan Check Engineer 5/31/2022 PINANK PATEL
Corrections Issued 6/1/2022 PINANK PATEL
Building Plans Picked Up 7/29/2022 APPLICANT
Applicant returned to address corrections 3/7/2023 JESSE ARELLANO
Issued 3/9/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/6/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 9/6/2022 ROBERT HUGHES
Roof/Waste drainage to street Cleared 9/6/2022 COLIN LOREDO
Specific Plan Cleared 2/27/2023 CECILIA CASTILLO
ZI Cleared 2/27/2023 CECILIA CASTILLO
Eng Process Fee Ord 176,300 Cleared 3/7/2023 COLIN LOREDO
Private sewage disp. approval Cleared 3/7/2023 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/3/2023 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 9/11/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/16/2025 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Not Ready for Inspection WILLIAM WREN
Green Building Rough 10/16/2025 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 10/30/2025 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 10/30/2025 Corrections Issued CRAIG DAVIS
Green Building Rough 10/30/2025 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 10/30/2025 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 10/30/2025 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 11/7/2025 Approved WILLIAM WREN
ELECTRICAL-Rough 11/7/2025 Approved WILLIAM WREN
Green Building Rough 11/7/2025 Approved WILLIAM WREN
Interior/Exterior Lathing 11/7/2025 Approved WILLIAM WREN
PLUMBING-Rough 11/7/2025 Approved WILLIAM WREN
BUILDING-Rough-Frame 3/19/2026 Approved MATTHEW NELSON
HVAC-Rough 3/19/2026 Approved MATTHEW NELSON
Insulation 3/19/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/19/2026 Approved MATTHEW NELSON
Drywall Nailing 5/1/2026 Approved NICHOLAS TROWBRIDGE