5049 N VINCENT AVE 90041
Certificate Information: 5049 N VINCENT AVE 90041
- Application / Permit
- 22014-20000-02498
- Plan Check / Job No.
- B22VN07920
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 25'-6" x 25'-6" (441 SQ. FT.) IRREGULAR SHAPED ADDITION TO THE (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/6/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Applicant returned to address corrections | 7/21/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/15/2022 | OMAR GARNICA |
| Issued | 11/6/2023 | APPLICANT |
| CofO in Progress | 5/2/2024 | CHARLES BOGHOSKHAN |
| Permit Finaled | 5/6/2024 | DEROLD HAUFF |
| CofO Issued | 5/6/2024 | DEROLD HAUFF |
| Permit Finaled | 5/6/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/17/2022 | AMAAN MALIK |
| Grading Pre-Inspection | Cleared | 6/27/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/28/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/7/2023 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/15/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/17/2023 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 11/17/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/21/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/21/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/27/2023 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 11/27/2023 | Corrections Issued | JEFFREY MEAD |
| Wood Frame | 11/27/2023 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/4/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 12/4/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 12/4/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/4/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 12/4/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 12/6/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/6/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 12/8/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/24/2024 | Approved | CRAIG VAUGHAN |
| Final | 4/24/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 4/24/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/24/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/24/2024 | Corrections Issued | CRAIG VAUGHAN |
| Final | 5/1/2024 | OK to Issue CofO | CHARLES BOGHOSKHAN |
| Smoke Detectors | 5/1/2024 | Approved | CHARLES BOGHOSKHAN |
| Smoke Detectors | 5/2/2024 | Approved | CHARLES BOGHOSKHAN |