5525 N CARPENTER AVE 91607

Certificate Information: 5525 N CARPENTER AVE 91607

Application / Permit
22014-20000-02464
Plan Check / Job No.
B22VN07824
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL, REMOVE (E) ROOF, 24'-11" X 13'-5" & 32'-6" X 42'-1" IRREGULAR SHAPED ADDITIONS TO (E) SFD. FIRE SPRINKLER REQUIRED THROUGHOUT.
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
Issued on 8/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/19/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 ARTIN ZARUKIAN
Corrections Issued 5/21/2022 ARTIN ZARUKIAN
Building Plans Picked Up 5/25/2022 APPLICANT
Issued 8/30/2023 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 12/5/2022 JOANNA MARROQUIN
ZI Cleared 12/5/2022 JOANNA MARROQUIN
ZI Cleared 12/5/2022 JOANNA MARROQUIN
Eng Process Fee Ord 176,300 Cleared 12/6/2022 LEE GUILBEAUX
Sewer availability Cleared 12/6/2022 LEE GUILBEAUX
Low Impact Development Cleared 8/7/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/22/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2024 Corrections Issued KIRK SANDERS
Deputy Drilled-In Anchors 1/22/2024 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 1/25/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/26/2024 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 2/6/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 2/7/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 2/23/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 3/1/2024 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/8/2024 Partial Approval CHRISTOPHE COCHRAN
Pre-Inspection 3/8/2024 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/21/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 3/21/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/21/2024 Corrections Issued KIRK SANDERS
Green Building Rough 3/21/2024 Not Ready for Inspection KIRK SANDERS
MERV13>=Rough 3/21/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 3/21/2024 Not Ready for Inspection KIRK SANDERS
Sewer 3/21/2024 Not Ready for Inspection KIRK SANDERS
Wood Frame 3/21/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 4/11/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/11/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 4/11/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 4/11/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 4/11/2024 Partial Approval CHRISTOPHER ROJAS
Wood Frame 4/11/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/16/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/24/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/29/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 5/9/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 5/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/21/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 6/4/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 6/4/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/13/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/15/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 7/15/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/15/2024 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/15/2024 Partial Approval CHRISTOPHER ROJAS
Sewer 7/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 7/15/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/15/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 8/15/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 8/15/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/15/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 8/26/2024 Corrections Issued CHRISTOPHER ROJAS
Insulation 8/28/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 9/3/2024 Approved MICHAEL CORTEZ
Shower Pan 9/3/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 2/3/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 3/17/2026 Corrections Issued JAVIER RAMOS JR
Final 3/17/2026 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 3/17/2026 Approved JAVIER RAMOS JR
Green Building Final 3/17/2026 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 3/17/2026 Corrections Issued JAVIER RAMOS JR
MERV13>=Final 3/17/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 3/17/2026 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 3/17/2026 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 3/17/2026 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 5/12/2026 Approved WAYNE REGESTER
ELECTRICAL-Final 5/12/2026 Corrections Issued WAYNE REGESTER
Final 5/12/2026 Not Ready for Inspection WAYNE REGESTER
Green Building Final 5/12/2026 Approved WAYNE REGESTER
HVAC-Final 5/12/2026 Approved WAYNE REGESTER
PLUMBING-Final 5/12/2026 Approved WAYNE REGESTER