609 N CHEROKEE AVE 90004

Certificate Information: 609 N CHEROKEE AVE 90004

Application / Permit
22014-20000-02463
Plan Check / Job No.
B22VN07820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
8'-5 1/2" X 15'-2" ADDITION TO AND CONVERT THE (E) 479 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 SERGIO MUNIZ
Corrections Issued 5/21/2022 SERGIO MUNIZ
Building Plans Picked Up 5/26/2022 APPLICANT
Plan Check Approved 9/15/2022 OMAR GARNICA
Issued 9/15/2022 APPLICANT
CofO in Progress 5/10/2024 ROY SPAULDING
Permit Finaled 3/29/2025 DEROLD HAUFF
CofO Issued 3/29/2025 DEROLD HAUFF
Permit Finaled 3/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/3/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 6/3/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/13/2022 STEVE MELGAR
Sewer availability Cleared 6/13/2022 STEVE MELGAR
HPOZ Cleared 8/2/2022 SUKI GERSHENHORN
Miscellaneous Cleared 8/2/2022 SUKI GERSHENHORN
Construction near power lines Cleared 8/22/2022 RIDWAN HARDY

Contact Information

Architect Tohill,, Kevin Patrick; Lic. No.: C32787 3790 LIGHTNING RIDGE WAY      SIMI VALLEY, CA 93063
Contractor Mc Burney Matthew Construction; Lic. No.: 509046-B 21427 DE LA OSA STREET      WOODLAND HILLS, CA 91364
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/3/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/9/2023 Partial Approval RAUL BARAJAS
METHANE-Barrier 3/9/2023 Not Ready for Inspection RAUL BARAJAS
METHANE-Subgrade 3/9/2023 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/3/2023 Partial Approval JOAQUIN GREENOUGH
METHANE-Barrier 4/3/2023 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 4/3/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/8/2023 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 5/18/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 8/8/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 8/8/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 8/8/2023 Approved JOAQUIN GREENOUGH
Wood Frame 8/8/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/17/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 8/17/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 8/17/2023 Approved JOAQUIN GREENOUGH
METHANE-Rough 8/17/2023 Approved JOAQUIN GREENOUGH
Insulation 8/25/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/25/2023 Partial Approval JOAQUIN GREENOUGH
Drywall Nailing 9/5/2023 Approved JOAQUIN GREENOUGH
Shower Pan 9/11/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 9/18/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Shower Pan 9/18/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/21/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/21/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 9/21/2023 Approved JOAQUIN GREENOUGH
Sewer 9/21/2023 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 9/21/2023 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/26/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 9/26/2023 Approved JOAQUIN GREENOUGH
Underground Mechanical 9/26/2023 Approved JOAQUIN GREENOUGH
Grounding or Bonding 11/21/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 2/22/2024 Corrections Issued BRENDAN MORELLI
Final 2/22/2024 Corrections Issued BRENDAN MORELLI
HVAC-Final 2/22/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 2/22/2024 Corrections Issued BRENDAN MORELLI
Final 5/1/2024 Corrections Issued ROY SPAULDING
Green Building Final 5/1/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 5/1/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 5/1/2024 Approved ROY SPAULDING
Final 5/9/2024 OK to Issue CofO ROY SPAULDING