6366 W 84TH ST 90045
Certificate Information: 6366 W 84TH ST 90045
- Application / Permit
- 22014-20000-02444
- Plan Check / Job No.
- B22VN07760
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL INT AND EXT WALLS EXCEPT FOR 3' EXT WALL @ WEST SIDE AND ERECT IRR SHAPED 38'-5" x 55'-6" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 4/6/2023
- Issuing Office
- Current Status
- CofO Issued on 5/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | SEAN SHAHMIRI |
| Corrections Issued | 6/6/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 6/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| Plan Check Approved | 4/6/2023 | SEAN SHAHMIRI |
| Issued | 4/6/2023 | APPLICANT |
| Permit Closed-Status Void | 4/11/2025 | RUBEN RIVAS |
| Re-Activate Permit | 4/14/2025 | RUBEN RIVAS |
| CofO in Progress | 4/14/2025 | DAVID FEILER |
| CofO in Progress | 4/15/2025 | DAVID FEILER |
| CofO in Progress | 5/1/2025 | DAVID FEILER |
| Permit Finaled | 5/1/2025 | RICHARD STEINBACH |
| CofO Issued | 5/1/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/1/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 6/13/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2022 | DINAH GARIN |
| Sewer availability | Cleared | 6/23/2022 | DINAH GARIN |
| Specific Plan | Cleared | 9/6/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 10/20/2022 | LUIS LUVANO |
| Trees in Parkway | Cleared | 11/9/2022 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 1/6/2023 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/17/2023 | Partial Inspection | HERBERT GIRON |
| PLUMBING-Rough | 7/20/2023 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 8/14/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 8/14/2023 | Conditional Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Structural Steel Frame | 10/24/2023 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 10/24/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Underground Mechanical | 11/2/2023 | Partial Approval | RICHARD STEINBACH |
| Pre-Inspection | 12/1/2023 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | TEMISTOCLES CAAL |
| Underground Mechanical | 2/15/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 3/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 3/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/13/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 3/13/2024 | Partial Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 3/19/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 3/19/2024 | Approved | BOBBY KEY |
| Green Building Rough | 3/19/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 3/19/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/19/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 3/19/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 3/29/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/29/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 3/29/2024 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 3/29/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 5/14/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/14/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/15/2024 | Approved | JESUS PINEDA |
| Pre-Inspection | 5/16/2024 | Partial Inspection | RICHARD STEINBACH |
| ELECTRICAL-Final | 3/11/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Final | 3/11/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Final | 3/11/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Special/Order Compliance | 3/11/2025 | Partial Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/1/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 4/1/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 4/1/2025 | Approved | RUBEN RIVAS |
| Final | 4/11/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Footing/Foundation/Slab | 4/11/2025 | Approved | RUBEN RIVAS |
| Green Building Final | 4/11/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 4/11/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 4/15/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 5/1/2025 | OK to Issue CofO | DAVID FEILER |