6201 N WILLOW CREST AVE 91606

Certificate Information: 6201 N WILLOW CREST AVE 91606

Application / Permit
22014-20000-02437
Plan Check / Job No.
B22VN07716
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE 20'X35'-2" ONE STORY ADDITION TO (E) SFD AND CONNECT TO EXISTING DETACHED GARAGE WITH 4'-5"X20'-2" ATTACHED STORAGE WITH EXTERIOR ACCESS_ ENTIRE BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 11/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 DAWN MC NULTY
Corrections Issued 5/31/2022 DAWN MC NULTY
Quality Review Completed 6/2/2022 STEVEN KIM
Building Plans Picked Up 6/22/2022 APPLICANT
Applicant returned to address corrections 11/3/2022 DAWN MC NULTY
Plan Check Approved 11/9/2022 DAWN MC NULTY
Issued 11/10/2022 APPLICANT
CofO in Progress 3/2/2023 JOHN HAYES
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 6/13/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/14/2022 MEGAN GODINEZ
Sewer availability Cleared 6/14/2022 MEGAN GODINEZ
Low Impact Development Cleared 7/15/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 11/4/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/18/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 11/22/2022 Approved DAVID ANDERSON
Insulation 12/1/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/1/2022 Partial Approval JOHN HAYES
Wood Frame 12/1/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Approved JOHN HAYES
Deputy Wood Construction 12/21/2022 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 12/29/2022 Approved JOHN HAYES
ELECTRICAL-Rough 12/29/2022 Approved JOHN HAYES
Gas Test 12/29/2022 Approved JOHN HAYES
Green Building Rough 12/29/2022 Approved JOHN HAYES
HVAC-Rough 12/29/2022 Approved JOHN HAYES
Interior/Exterior Lathing 12/29/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 12/29/2022 Approved JOHN HAYES
Wood Frame 12/29/2022 Approved JOHN HAYES
Insulation 1/3/2023 Approved JOHN HAYES
Drywall Nailing 1/9/2023 Approved DAVID ANDERSON
Shower Pan 1/9/2023 Approved DAVID ANDERSON
Final 2/17/2023 Corrections Issued JOHN HAYES
Green Building Final 2/17/2023 Approved JOHN HAYES
Service/Power Release 2/17/2023 Not Ready for Inspection JOHN HAYES
Verify Rec and Parks Fee Memo 2/17/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 2/27/2023 Approved JOHN HAYES
Final 2/27/2023 Corrections Issued JOHN HAYES
HVAC-Final 2/27/2023 Approved JOHN HAYES
PLUMBING-Final 2/27/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 2/27/2023 Approved JOHN HAYES
ELECTRICAL-Final 3/2/2023 Approved JOHN HAYES
Final 3/2/2023 OK to Issue CofO JOHN HAYES
HVAC-Final 3/2/2023 Approved JOHN HAYES
PLUMBING-Final 3/2/2023 Approved JOHN HAYES