7124 N LASAINE AVE 91406

Certificate Information: 7124 N LASAINE AVE 91406

Application / Permit
22014-20000-02434
Plan Check / Job No.
B22VN07704
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 19'-6" X 3'-9" COVERED PATIO AS PART OF DWELLING; ADD 5'-4" X 10' PORCH IN THE FRONT OF THE DWELLING
Permit Issued
Issued on 1/25/2023
Issuing Office
Current Status
Issued on 1/25/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 SELLA BENYAMIN
Corrections Issued 6/13/2022 SELLA BENYAMIN
Quality Review Completed 6/22/2022 STEVEN KIM
Building Plans Picked Up 6/28/2022 APPLICANT
Plan Check Approved 10/4/2022 SELLA BENYAMIN
Issued 1/25/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/29/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 9/19/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/19/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 9/19/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 9/19/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Ondaine Enterprises; Lic. No.: 750898-B 9725 PENFIELD AVE      CHATSWORTH, CA 91311
Engineer Abkarian,, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/30/2023 Corrections Issued JON MCHUGH
Pre-Inspection 8/30/2023 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 9/7/2023 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 9/7/2023 Not Ready for Inspection JON MCHUGH
Excavation/Setback/Form/Re-Bar 9/20/2023 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 9/20/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 9/25/2023 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 10/3/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Partial Approval JON MCHUGH
Insulation 10/3/2023 Partial Approval JON MCHUGH
ELECTRICAL-Rough 12/5/2023 Not Ready for Inspection JON MCHUGH
Wood Frame 12/5/2023 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 3/6/2024 Corrections Issued JON MCHUGH
Green Building Rough 3/6/2024 Not Ready for Inspection JON MCHUGH
Wood Frame 3/6/2024 Not Ready for Inspection JON MCHUGH
Deputy Drilled-In Anchors 3/8/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 3/12/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 3/26/2024 Not Ready for Inspection HORACE FULTZ
Green Building Rough 3/26/2024 Approved HORACE FULTZ
PLUMBING-Rough 3/26/2024 Approved HORACE FULTZ
BUILDING-Rough-Frame 4/9/2024 Approved JON MCHUGH
ELECTRICAL-Rough 4/9/2024 Corrections Issued JON MCHUGH
HVAC-Rough 4/9/2024 Corrections Issued JON MCHUGH
PLUMBING-Rough 4/9/2024 Approved JON MCHUGH
ELECTRICAL-Rough 4/11/2024 Partial Approval JON MCHUGH
Insulation 4/11/2024 Approved JON MCHUGH
Drywall Nailing 5/7/2024 Approved HENRY KIM
Special/Order Compliance 5/7/2024 Corrections Issued HENRY KIM
Final 5/7/2025 Corrections Issued JON MCHUGH
Green Building Final 5/7/2025 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved JON MCHUGH
Smoke Detectors 5/7/2025 Approved JON MCHUGH
Final 7/1/2025 Corrections Issued JON MCHUGH
Green Building Final 7/1/2025 Not Ready for Inspection JON MCHUGH