1916 W COURT ST 90026
Certificate Information: 1916 W COURT ST 90026
- Application / Permit
- 22014-20000-02424
- Plan Check / Job No.
- B22VN07668
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL INT AND EXT WALLS EXCEPT FOR PORTION OF FRONT AND SIDE WALLS AND ERECT 21'-6" x 37' TWO STORY SINGLE FAMILY DWELLING W/ ATT. WOOD DECK; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 11/16/2022
- Issuing Office
- Current Status
- CofO Issued on 11/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | SEAN SHAHMIRI |
| Corrections Issued | 6/15/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 6/16/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/17/2022 | APPLICANT |
| Applicant returned to address corrections | 7/23/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 10/5/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 11/14/2022 | SEAN SHAHMIRI |
| Issued | 11/16/2022 | APPLICANT |
| CofO in Progress | 10/31/2023 | FREDDIE RIVERA |
| Permit Finaled | 11/5/2023 | DEROLD HAUFF |
| CofO Issued | 11/5/2023 | DEROLD HAUFF |
| Permit Finaled | 11/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/10/2022 | SEAN SHAHMIRI |
| Certificate of Compliance | Cleared | 6/21/2022 | MIGUEL GAMBOA |
| Frnt yard landscape/Water mgmt | Cleared | 6/21/2022 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 6/24/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 10/4/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/6/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Partial Inspection | FREDDIE RIVERA |
| Pre-Inspection | 12/1/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/15/2022 | Partial Approval | FREDDIE RIVERA |
| METHANE-Barrier | 12/15/2022 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 12/15/2022 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/28/2022 | Partial Approval | FREDDIE RIVERA |
| METHANE-Subgrade | 12/28/2022 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/9/2023 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/12/2023 | Corrections Issued | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 1/13/2023 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/17/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/6/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 2/6/2023 | Partial Approval | FREDDIE RIVERA |
| Insulation | 2/7/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Partial Approval | FREDDIE RIVERA |
| Wood Frame | 2/8/2023 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/13/2023 | Approved | STUART CHAPMAN |
| Final | 4/13/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 4/13/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/13/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 4/13/2023 | Corrections Issued | STUART CHAPMAN |
| Shower Pan | 4/13/2023 | Approved | STUART CHAPMAN |
| Insulation | 4/18/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/18/2023 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 4/20/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/20/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/25/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 6/6/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 6/6/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 6/30/2023 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 6/30/2023 | Approved | FREDDIE RIVERA |
| HVAC-Final | 6/30/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 6/30/2023 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 7/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/6/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/11/2023 | Not Ready for Inspection | FREDDIE RIVERA |
| Service/Power Release | 7/11/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | FREDDIE RIVERA |
| Final | 10/31/2023 | OK to Issue CofO | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/31/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 10/31/2023 | Approved | FREDDIE RIVERA |
| METHANE-Final | 10/31/2023 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 10/31/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 10/31/2023 | Approved | FREDDIE RIVERA |