1916 W COURT ST 90026

Certificate Information: 1916 W COURT ST 90026

Application / Permit
22014-20000-02424
Plan Check / Job No.
B22VN07668
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL INT AND EXT WALLS EXCEPT FOR PORTION OF FRONT AND SIDE WALLS AND ERECT 21'-6" x 37' TWO STORY SINGLE FAMILY DWELLING W/ ATT. WOOD DECK; NFPA-13D THRU-OUT
Permit Issued
Issued on 11/16/2022
Issuing Office
Current Status
CofO Issued on 11/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 SEAN SHAHMIRI
Corrections Issued 6/15/2022 SEAN SHAHMIRI
Quality Review Completed 6/16/2022 OMID HEDAYAT
Building Plans Picked Up 6/17/2022 APPLICANT
Applicant returned to address corrections 7/23/2022 SEAN SHAHMIRI
Applicant returned to address corrections 10/5/2022 SEAN SHAHMIRI
Plan Check Approved 11/14/2022 SEAN SHAHMIRI
Issued 11/16/2022 APPLICANT
CofO in Progress 10/31/2023 FREDDIE RIVERA
Permit Finaled 11/5/2023 DEROLD HAUFF
CofO Issued 11/5/2023 DEROLD HAUFF
Permit Finaled 11/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/10/2022 SEAN SHAHMIRI
Certificate of Compliance Cleared 6/21/2022 MIGUEL GAMBOA
Frnt yard landscape/Water mgmt Cleared 6/21/2022 MIGUEL GAMBOA
Sewer availability Cleared 6/24/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 6/27/2022 JEANETTE VONG
Low Impact Development Cleared 10/4/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/6/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2022 Partial Inspection FREDDIE RIVERA
Pre-Inspection 12/1/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 12/15/2022 Partial Approval FREDDIE RIVERA
METHANE-Barrier 12/15/2022 Approved FREDDIE RIVERA
METHANE-Subgrade 12/15/2022 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 12/28/2022 Partial Approval FREDDIE RIVERA
METHANE-Subgrade 12/28/2022 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/9/2023 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/12/2023 Corrections Issued FREDDIE RIVERA
Deputy Drilled-In Anchors 1/13/2023 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/17/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 2/6/2023 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 2/6/2023 Partial Approval FREDDIE RIVERA
Insulation 2/7/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval FREDDIE RIVERA
Wood Frame 2/8/2023 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 4/13/2023 Approved STUART CHAPMAN
Final 4/13/2023 Corrections Issued STUART CHAPMAN
HVAC-Rough 4/13/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 4/13/2023 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/13/2023 Corrections Issued STUART CHAPMAN
Shower Pan 4/13/2023 Approved STUART CHAPMAN
Insulation 4/18/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/18/2023 Partial Approval FREDDIE RIVERA
Drywall Nailing 4/20/2023 Approved FREDDIE RIVERA
Green Building Rough 4/20/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/25/2023 Approved FREDDIE RIVERA
ELECTRICAL-Final 6/6/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 6/6/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 6/30/2023 Corrections Issued FREDDIE RIVERA
Gas Test 6/30/2023 Approved FREDDIE RIVERA
HVAC-Final 6/30/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Final 6/30/2023 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 7/6/2023 Approved ALIZAH MAYAGOITIA
Final 7/6/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 7/6/2023 Approved ALIZAH MAYAGOITIA
Final 7/11/2023 Not Ready for Inspection FREDDIE RIVERA
Service/Power Release 7/11/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/31/2023 Approved FREDDIE RIVERA
Final 10/31/2023 OK to Issue CofO FREDDIE RIVERA
Footing/Foundation/Slab 10/31/2023 Approved FREDDIE RIVERA
Green Building Final 10/31/2023 Approved FREDDIE RIVERA
METHANE-Final 10/31/2023 Approved FREDDIE RIVERA
METHANE-Rough 10/31/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 10/31/2023 Approved FREDDIE RIVERA