8334 N WILBUR AVE 91324

Certificate Information: 8334 N WILBUR AVE 91324

Application / Permit
22014-20000-02409
Plan Check / Job No.
B22VN07610
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19' X 18'-3" ADDITION TO ENLARGE BEDROOM AND REMODEL BATHROOM PER ENGINEER.
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
CofO Issued on 3/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 JEROME MAGAT PALMA
Corrections Issued 5/21/2022 JEROME MAGAT PALMA
Building Plans Picked Up 5/23/2022 APPLICANT
Applicant returned to address corrections 6/7/2022 JEROME MAGAT PALMA
Plan Check Approved 6/21/2022 JEROME MAGAT PALMA
Issued 6/21/2022 APPLICANT
CofO in Progress 12/12/2022 CHRIS CHRISTENSEN
Permit Finaled 3/18/2023 DANIEL ORRANTE
CofO Issued 3/18/2023 DANIEL ORRANTE
Permit Finaled 3/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/9/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/9/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/9/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/9/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/9/2022 MEGAN GODINEZ

Contact Information

Contractor Quality Home Renovators Inc; Lic. No.: 959548-B 2290 AGATE CT UNIT A-B      SIMI VALLEY, CA 93065
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/7/2022 Conditional Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 9/12/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/12/2022 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 9/26/2022 Approved JUSTIN HAWLEY
PLUMBING-Rough 9/26/2022 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 10/12/2022 Partial Approval JOHN KIDWELL
Green Building Rough 10/12/2022 Partial Approval JOHN KIDWELL
Insulation 10/24/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/24/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 10/24/2022 Approved DAVID SCANTLIN
Drywall Nailing 10/31/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 11/23/2022 Approved JOHN KIDWELL
Final 11/23/2022 Corrections Issued JOHN KIDWELL
Green Building Rough 11/23/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 11/23/2022 Approved JOHN KIDWELL
Special/Order Compliance 11/23/2022 Corrections Issued JON MCHUGH
ELECTRICAL-Final 12/9/2022 Approved CHRIS CHRISTENSEN
Final 12/9/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 12/9/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 12/9/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 12/9/2022 Approved CHRIS CHRISTENSEN