8334 N WILBUR AVE 91324
Certificate Information: 8334 N WILBUR AVE 91324
- Application / Permit
- 22014-20000-02409
- Plan Check / Job No.
- B22VN07610
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19' X 18'-3" ADDITION TO ENLARGE BEDROOM AND REMODEL BATHROOM PER ENGINEER.
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 5/21/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/23/2022 | APPLICANT |
| Applicant returned to address corrections | 6/7/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 6/21/2022 | JEROME MAGAT PALMA |
| Issued | 6/21/2022 | APPLICANT |
| CofO in Progress | 12/12/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/9/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/9/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/9/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Quality Home Renovators Inc; Lic. No.: 959548-B | 2290 AGATE CT UNIT A-B SIMI VALLEY, CA 93065 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2022 | Conditional Approval | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/12/2022 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 9/26/2022 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 9/26/2022 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 10/12/2022 | Partial Approval | JOHN KIDWELL |
| Insulation | 10/24/2022 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/24/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 10/24/2022 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 10/31/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | JOHN KIDWELL |
| Final | 11/23/2022 | Corrections Issued | JOHN KIDWELL |
| Green Building Rough | 11/23/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 11/23/2022 | Approved | JOHN KIDWELL |
| Special/Order Compliance | 11/23/2022 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 12/9/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 12/9/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 12/9/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 12/9/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 12/9/2022 | Approved | CHRIS CHRISTENSEN |