3414 S MAPLEWOOD AVE 90066
Certificate Information: 3414 S MAPLEWOOD AVE 90066
- Application / Permit
- 22014-20000-02400
- Plan Check / Job No.
- B22VN07575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 18'-0" X 7'-1" ADDITION TO AND CONVERT THE (E) 18' x 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 5/21/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/23/2022 | APPLICANT |
| Applicant returned to address corrections | 7/26/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 8/10/2022 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 8/23/2022 | JESSE ARELLANO |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 2/3/2023 | MICHAEL PELHAM |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
| CofO Issued | 2/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 5/24/2022 | MEGAN GODINEZ |
| Specific Plan | Cleared | 6/1/2022 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 7/26/2022 | ARTIN ZARUKIAN |
| Sewer availability | Cleared | 8/11/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 8/11/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 8/11/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 8/11/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/20/2022 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/20/2022 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/24/2022 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/14/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/14/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 11/14/2022 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/14/2022 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 11/28/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/28/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/28/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 11/28/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 12/2/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 12/2/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 12/2/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 1/19/2023 | Approved | JESUS RODRIGUEZ |
| Final | 1/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 1/19/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/19/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 1/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| Final | 2/1/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 2/1/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 2/1/2023 | Approved | JESUS RODRIGUEZ |