15001 W KITTRIDGE ST 91405
Certificate Information: 15001 W KITTRIDGE ST 91405
- Application / Permit
- 22014-20000-02378
- Plan Check / Job No.
- B22VN07484
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 25'-11" x 20'-4" TO AND CONVERT 20'-4" x 20'-1" GARAGE TO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Current Status
- CofO Issued on 4/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 5/19/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Applicant returned to address corrections | 10/24/2022 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 12/1/2022 | ALEC MOUSAKHANIAN |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 3/31/2023 | RYAN SALAZAR |
| Permit Finaled | 4/17/2023 | MICHAEL SMITH |
| CofO Issued | 4/17/2023 | MICHAEL SMITH |
| Permit Finaled | 4/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 6/7/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 10/18/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/1/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | La Top Builders Inc; Lic. No.: 1077576-B | 20701 EXHIBIT PLACE WOODLAND HILLS, CA 91367 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/6/2022 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 12/13/2022 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 1/12/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 1/18/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/18/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/18/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/18/2023 | Approved | RYAN SALAZAR |
| Insulation | 1/23/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/23/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 1/23/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/27/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/1/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | RYAN SALAZAR |
| Final | 3/6/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 3/6/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 3/6/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/6/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 3/6/2023 | Approved | RYAN SALAZAR |
| Final | 3/31/2023 | OK to Issue CofO | RYAN SALAZAR |