8390 S STEWART AVE 90045
Certificate Information: 8390 S STEWART AVE 90045
- Application / Permit
- 22014-20000-02366
- Plan Check / Job No.
- B22VN07452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) DETACHED GARAGE AND ADD IRR.-SHAPE 2-STORY ACCESSORY DWELLING UNIT TO (E) DETACHED GARAGE. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 5/28/2022 | GURUNATH NESARAJAH |
| Quality Review Completed | 6/2/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| Applicant returned to address corrections | 11/30/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/14/2022 | GURUNATH NESARAJAH |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 1/2/2026 | JESUS PINEDA |
| Permit Finaled | 1/5/2026 | RICHARD STEINBACH |
| CofO Issued | 1/5/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/5/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2022 | JOSE HERNANDEZ |
| Construction near power lines | Cleared | 7/6/2022 | TINA MIRANDA |
| Specific Plan | Cleared | 10/14/2022 | EDUARDO HERMOSO |
| Low Impact Development | Cleared | 10/21/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/26/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | AHMED AMARRAGY |
| Sewer availability | Cleared | 10/31/2022 | AHMED AMARRAGY |
Contact Information
| Contractor | O P M Construction Inc; Lic. No.: 1110738-B | 1245 MENLO AVE LOS ANGELES, CA 90006 |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/28/2024 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 9/3/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/6/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/17/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 9/17/2024 | Corrections Issued | BOBBY KEY |
| Deputy Drilled-In Anchors | 10/9/2024 | Conditional Approval | BOBBY KEY |
| Underground Mechanical | 11/19/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/20/2024 | Approved | TEMISTOCLES CAAL |
| Sewer | 11/20/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Corrections Issued | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 2/5/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 2/10/2025 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/10/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 3/10/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 3/10/2025 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 3/10/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 3/10/2025 | Approved | JESUS PINEDA |
| Rough-Elec/Plmb/HVAC | 3/10/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 3/10/2025 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | BOBBY KEY |
| Green Building Rough | 4/17/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/17/2025 | Partial Approval | BOBBY KEY |
| Service/Power Release | 4/17/2025 | Not Ready for Inspection | BOBBY KEY |
| Shower Pan | 4/17/2025 | Approved | BOBBY KEY |
| Insulation | 4/23/2025 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 4/23/2025 | Not Ready for Inspection | JESUS PINEDA |
| Insulation | 4/24/2025 | Not Ready for Inspection | JESUS PINEDA |
| Service/Power Release | 4/24/2025 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 4/30/2025 | Approved | JAYLIN GRAVITTE |
| Insulation | 4/30/2025 | Approved | JAYLIN GRAVITTE |
| Special/Order Compliance | 4/30/2025 | Partial Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 5/12/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 8/6/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/6/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 8/6/2025 | Corrections Issued | JESUS PINEDA |
| Smoke Detectors | 8/6/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 8/13/2025 | Not Ready for Inspection | JESUS PINEDA |
| Final | 8/13/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/13/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/13/2025 | Not Ready for Inspection | JESUS PINEDA |
| PLUMBING-Final | 8/13/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 8/13/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 8/18/2025 | Approved | JESUS PINEDA |
| Gas Test | 8/18/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 8/18/2025 | Not Ready for Inspection | JESUS PINEDA |
| Final | 9/25/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Final | 9/25/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 9/25/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 9/25/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/25/2025 | SGSOV Approved | JESUS PINEDA |
| Final | 9/30/2025 | Not Ready for Inspection | JESUS PINEDA |
| Final | 1/2/2026 | OK to Issue CofO | JESUS PINEDA |