3805 3/4 S DENKER AVE 90062

Certificate Information: 3805 3/4 S DENKER AVE 90062

Application / Permit
22014-20000-02350
Plan Check / Job No.
B22VN07416
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
10'-5" X 20'-2" (210 SQ. FT.) ADDITION TO AND CONVERT THE (E) 484 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2022 APPLICANT
Assigned to Plan Check Engineer 5/18/2022 OMAR GARNICA
Corrections Issued 5/19/2022 OMAR GARNICA
Plan Check Approved 7/13/2022 OMAR GARNICA
Building Plans Picked Up 7/14/2022 APPLICANT
Issued 10/14/2022 APPLICANT
CofO in Progress 8/1/2023 STUART CHAPMAN
CofO Issued 8/22/2023 RONALD MYRICK
Permit Finaled 8/22/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 6/29/2022 CINDY QI
Roof/Waste drainage to street Cleared 6/29/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/7/2022 CINDY QI
Sewer availability Cleared 7/7/2022 CINDY QI

Contact Information

Contractor Diaz Leonardo Alfredo; Lic. No.: 954891-B 130 NORTH ARDMORE AVENUE      LOS ANGELES, CA 90004
Engineer Medina,, Armando; Lic. No.: C83911 2000 W LINCOLN AVE      MONTEBELLO, CA 90640

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/27/2022 Approved SABAS ALONSO
Underground Mechanical 11/14/2022 Approved SABAS ALONSO
Excavation/Setback/Form/Re-Bar 11/29/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 11/29/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 2/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 2/2/2023 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/9/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Approved SABAS ALONSO
Green Building Rough 2/9/2023 Not Ready for Inspection SABAS ALONSO
Wood Frame 2/9/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 2/17/2023 Corrections Issued SABAS ALONSO
Green Building Rough 2/17/2023 Approved SABAS ALONSO
HVAC-Rough 2/17/2023 Approved SABAS ALONSO
PLUMBING-Rough 2/17/2023 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 2/23/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 2/23/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 2/23/2023 Partial Approval SABAS ALONSO
PLUMBING-Rough 2/23/2023 Approved SABAS ALONSO
Insulation 3/1/2023 Partial Approval SABAS ALONSO
Drywall Nailing 3/7/2023 Approved ALEJANDRO DE ARTOLA
Shower Pan 3/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/31/2023 Approved SABAS ALONSO
Shower Pan 3/31/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 4/20/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Final 5/9/2023 Corrections Issued LILIANA PORTILLO
Final 5/9/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 5/9/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 5/9/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 5/9/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 5/9/2023 Corrections Issued LILIANA PORTILLO
Final 5/30/2023 Corrections Issued STUART CHAPMAN
Green Building Final 5/30/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 5/30/2023 Approved STUART CHAPMAN
Final 7/27/2023 OK to Issue CofO STUART CHAPMAN