18924 W VOSE ST 91335
Certificate Information: 18924 W VOSE ST 91335
- Application / Permit
- 22014-20000-02349
- Plan Check / Job No.
- B22VN07413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 7'-5"x17' FT. ADDITION TO AND CONVERT THE (E) 386.5 SQ. FT. ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 7/11/2022
- Issuing Office
- Current Status
- CofO Issued on 4/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2022 | JESSE ARELLANO |
| Corrections Issued | 5/19/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 7/8/2022 | JESSE ARELLANO |
| Plan Check Approved | 7/11/2022 | JESSE ARELLANO |
| Issued | 7/11/2022 | APPLICANT |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| CofO in Progress | 4/10/2024 | JEFFREY BULL |
| Permit Finaled | 4/26/2024 | JOHN JANSON |
| CofO Issued | 4/26/2024 | JOHN JANSON |
| Permit Finaled | 4/26/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2022 | CHRIS CHAHBAZ |
| Roof/Waste drainage to street | Cleared | 5/23/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 5/23/2022 | CHRIS CHAHBAZ |
| Green Code | Cleared | 7/8/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2022 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 7/15/2022 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 7/27/2022 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 8/1/2022 | Not Ready for Inspection | JEFFREY BULL |
| Deputy Drilled-In Anchors | 8/10/2022 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 8/15/2022 | Corrections Issued | JEFFREY BULL |
| PLUMBING-Rough | 8/15/2022 | Not Ready for Inspection | JEFFREY BULL |
| Footing/Foundation/Slab | 9/1/2022 | No Access for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 9/1/2022 | No Access for Inspection | JEFFREY BULL |
| Footing/Foundation/Slab | 9/2/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/2/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 11/3/2022 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Rough | 11/29/2022 | Not Ready for Inspection | SEAN WIRCH |
| HVAC-Rough | 11/29/2022 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 11/29/2022 | Corrections Issued | SEAN WIRCH |
| Wood Frame | 11/29/2022 | Corrections Issued | SEAN WIRCH |
| ELECTRICAL-Rough | 12/27/2022 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 1/13/2023 | Partial Inspection | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Partial Inspection | KRISTEN CAUSEY |
| Insulation | 1/13/2023 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 1/18/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 1/18/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 1/18/2023 | Approved | JEFFREY BULL |
| Wood Frame | 1/18/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 1/31/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 1/31/2023 | Approved | JEFFREY BULL |
| Shower Pan | 2/7/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 2/15/2023 | Approved | JUSTIN HAWLEY |
| Final | 4/19/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 4/19/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Not Ready | JEFFREY BULL |
| Smoke Detectors | 4/19/2023 | No Access for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 3/27/2024 | Approved | VINCENT HANLEY |
| Final | 3/27/2024 | Partial Approval | VINCENT HANLEY |
| HVAC-Final | 3/27/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/27/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 3/27/2024 | Approved | VINCENT HANLEY |
| Final | 4/10/2024 | OK to Issue CofO | JEFFREY BULL |