6306 N MELVIN AVE 91335

Certificate Information: 6306 N MELVIN AVE 91335

Application / Permit
22014-20000-02341
Plan Check / Job No.
B22VN07360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'4" X 21'10" ADDITION OF FAMILY ROOM TO (E) SFD. ALL WORK PER ENGINEER.
Permit Issued
Issued on 6/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2022 APPLICANT
Assigned to Plan Check Engineer 5/17/2022 PINANK PATEL
Corrections Issued 5/18/2022 PINANK PATEL
Building Plans Picked Up 5/19/2022 APPLICANT
Plan Check Approved 6/15/2022 JOSEPH RAFOLS
Issued 6/15/2022 APPLICANT
CofO in Progress 9/29/2022 STEVEN BACK
Permit Finaled 9/30/2022 JOHN JANSON
CofO Issued 9/30/2022 JOHN JANSON
Permit Finaled 9/30/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/2/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/27/2022 Approved STEVEN BACK
Footing/Foundation/Slab 6/27/2022 Approved STEVEN BACK
Deputy Drilled-In Anchors 6/28/2022 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Partial Approval STEVEN BACK
Insulation 6/30/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 7/18/2022 Approved STEVEN BACK
Interior/Exterior Lathing 7/18/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 7/18/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 7/21/2022 Approved STEVEN BACK
Deputy Wood Construction 7/21/2022 Approved STEVEN BACK
Green Building Rough 7/21/2022 Approved STEVEN BACK
HVAC-Rough 7/21/2022 Approved STEVEN BACK
Insulation 7/27/2022 Approved JESUS PINEDA
Drywall Nailing 8/2/2022 Approved KRISTEN CAUSEY
Final 9/23/2022 Corrections Issued STEVEN BACK
Green Building Final 9/23/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Gas Company STEVEN BACK
Smoke Detectors 9/23/2022 Approved STEVEN BACK
Final 9/29/2022 OK to Issue CofO STEVEN BACK