6306 N MELVIN AVE 91335
Certificate Information: 6306 N MELVIN AVE 91335
- Application / Permit
- 22014-20000-02341
- Plan Check / Job No.
- B22VN07360
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 13'4" X 21'10" ADDITION OF FAMILY ROOM TO (E) SFD. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 6/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2022 | PINANK PATEL |
| Corrections Issued | 5/18/2022 | PINANK PATEL |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| Plan Check Approved | 6/15/2022 | JOSEPH RAFOLS |
| Issued | 6/15/2022 | APPLICANT |
| CofO in Progress | 9/29/2022 | STEVEN BACK |
| Permit Finaled | 9/30/2022 | JOHN JANSON |
| CofO Issued | 9/30/2022 | JOHN JANSON |
| Permit Finaled | 9/30/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 6/27/2022 | Approved | STEVEN BACK |
| Deputy Drilled-In Anchors | 6/28/2022 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Partial Approval | STEVEN BACK |
| Insulation | 6/30/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 7/18/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/18/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 7/18/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/21/2022 | Approved | STEVEN BACK |
| Deputy Wood Construction | 7/21/2022 | Approved | STEVEN BACK |
| Green Building Rough | 7/21/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 7/21/2022 | Approved | STEVEN BACK |
| Insulation | 7/27/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 8/2/2022 | Approved | KRISTEN CAUSEY |
| Final | 9/23/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 9/23/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Gas Company | STEVEN BACK |
| Smoke Detectors | 9/23/2022 | Approved | STEVEN BACK |
| Final | 9/29/2022 | OK to Issue CofO | STEVEN BACK |