15919 W BASSETT ST 91406

Certificate Information: 15919 W BASSETT ST 91406

Application / Permit
22014-20000-02325
Plan Check / Job No.
B22VN07324
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(8'-1/2" X 19'-11") ADDITION TO THE FRONT OF THE (E) SFD, WITH A (5' X 19'-11") PATIO AT FRONT AND (18'-5" X 40'-1/2") REAR ADDITION. ALL WORK PER ENGINEER.
Permit Issued
Issued on 9/26/2022
Issuing Office
Metro
Current Status
Issued on 9/26/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/13/2022 APPLICANT
Assigned to Plan Check Engineer 5/17/2022 PINANK PATEL
Corrections Issued 5/17/2022 PINANK PATEL
Building Plans Picked Up 6/3/2022 APPLICANT
Plan Check Approved 9/19/2022 FARSHAD ALIMOHAMADI
Issued 9/26/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/9/2022 MEGAN GODINEZ
Low Impact Development Cleared 9/15/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/15/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/5/2022 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 10/12/2022 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 10/12/2022 Not Ready for Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 11/3/2022 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 11/3/2022 Not Ready for Inspection RAUL OLAGI
Pre-Inspection 11/9/2022 Approved RAUL OLAGI
Pre-Inspection 1/20/2023 Approved RAUL OLAGI
Deputy Drilled-In Anchors 1/25/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/9/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 2/13/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 3/2/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 3/16/2023 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 6/14/2023 Corrections Issued RAUL OLAGI
Deputy Wood Construction 6/21/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 7/11/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 7/11/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 7/11/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 7/11/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 7/18/2023 No Access for Inspection JUAN VALENZUELA
HVAC-Rough 7/18/2023 No Access for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 7/18/2023 No Access for Inspection JUAN VALENZUELA
PLUMBING-Rough 7/18/2023 No Access for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 7/20/2023 Conditional Approval JUAN VALENZUELA
Green Building Rough 7/20/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/20/2023 Partial Approval JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 7/20/2023 Approved JUAN VALENZUELA
Insulation 7/27/2023 Approved RAUL OLAGI
Shower Pan 7/27/2023 Approved RAUL OLAGI
Drywall Nailing 8/3/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/3/2023 Approved JUAN VALENZUELA