23454 W LADRILLO ST 91367
Certificate Information: 23454 W LADRILLO ST 91367
- Application / Permit
- 22014-20000-02317
- Plan Check / Job No.
- B22VN07313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDT'N OF (N) BEDROOM/BATHROOM (IRR 22'-5" X 31'-9") OVER (E) GARAGE OF 1-STORY SFD; INTERIOR REMODEL
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/21/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/23/2022 | STEVEN KIM |
| Building Plans Picked Up | 6/24/2022 | APPLICANT |
| Applicant returned to address corrections | 9/9/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/27/2022 | NILOOFAR MEHRAIN |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 3/10/2023 | TROY SANDERS |
| Permit Finaled | 3/22/2023 | JOHN JANSON |
| CofO Issued | 3/22/2023 | JOHN JANSON |
| Permit Finaled | 3/22/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/13/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 7/18/2022 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 8/3/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Tuggey Dave Construction; Lic. No.: 454278-B | 24371 HARTLAND STREET WEST HILLS, CA 91307 |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/4/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 10/18/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 10/18/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/18/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 10/28/2022 | Approved | TROY SANDERS |
| Green Building Rough | 10/28/2022 | Approved | TROY SANDERS |
| Insulation | 10/28/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/28/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 10/31/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/31/2022 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 11/14/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Final | 2/6/2023 | Approved | TROY SANDERS |
| Final | 2/6/2023 | Corrections Issued | TROY SANDERS |
| Footing/Foundation/Slab | 2/6/2023 | Approved | TROY SANDERS |
| Green Building Final | 2/6/2023 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 2/6/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 2/6/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/6/2023 | Approved | TROY SANDERS |
| Final | 3/10/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 3/10/2023 | Approved | TROY SANDERS |