6624 N NAGLE AVE 91401

Certificate Information: 6624 N NAGLE AVE 91401

Application / Permit
22014-20000-02308
Plan Check / Job No.
B22VN07286
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to an existing detached garage + Attached ADU to (E) garage Per LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
Issued on 6/29/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/15/2022 KHUONG TRUONG
Corrections Issued 5/17/2022 KHUONG TRUONG
Applicant returned to address corrections 5/26/2022 KHUONG TRUONG
Applicant returned to address corrections 6/2/2022 KHUONG TRUONG
Applicant returned to address corrections 6/5/2022 KHUONG TRUONG
Applicant returned to address corrections 6/18/2022 KHUONG TRUONG
Plan Check Approved 6/25/2022 KHUONG TRUONG
Issued 6/29/2022 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 5/24/2022 STEVEN WECHSLER
Address approval Cleared 5/24/2022 LEE GUILBEAUX
Low Impact Development Cleared 6/16/2022 SUNG JOON WON
Eng Process Fee Ord 176,300 Cleared 6/22/2022 ROSE MARIE SMITH
Sewer availability Cleared 6/22/2022 ROSE MARIE SMITH
Roof/Waste drainage to street Cleared 6/24/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/24/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI
GAREN HAYRAPETYAN, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/28/2022 Corrections Issued RAFAEL CORTES
PLUMBING-Rough 10/4/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 10/31/2022 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 11/14/2022 Conditional Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved KIRK SANDERS
PLUMBING-Rough 1/16/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 1/19/2024 Approved JOSE AVILA
Sewer 1/19/2024 Approved JOSE AVILA
Interior/Exterior Lathing 3/5/2024 Approved ROBERTO PALACIOS-LOPEZ