6535 N BELLINGHAM AVE 91606

Certificate Information: 6535 N BELLINGHAM AVE 91606

Application / Permit
22014-20000-02305
Plan Check / Job No.
B22VN07283
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 23'8" X 41' IRREGULAR SHAPED FIRSTAND SECOND FLOOR ADDITION TO AND CONVERT (E) 20'2" X 18'2" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)AND(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/6/2022
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 COLIN LOREDO
Corrections Issued 6/14/2022 COLIN LOREDO
Quality Review Completed 6/16/2022 OMID HEDAYAT
Building Plans Picked Up 6/27/2022 APPLICANT
Applicant returned to address corrections 8/25/2022 RARES BODEA
Plan Check Approved 9/6/2022 RARES BODEA
Issued 9/6/2022 APPLICANT
CofO in Progress 12/31/2024 ROBERTO PALACIOS-LOPEZ
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/1/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/8/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/8/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 7/25/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/27/2022 DAGOVERTO GUERRERO
ZI Cleared 8/2/2022 DAVID URITA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/1/2023 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 5/9/2023 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/11/2023 Approved DAVID ANDERSON
Deputy Wood Construction 6/1/2023 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/2/2023 Corrections Issued JOHN HAYES
Green Building Rough 6/2/2023 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 6/2/2023 Not Ready for Inspection JOHN HAYES
Deputy Drilled-In Anchors 6/12/2023 Conditional Approval MICHAEL SMITH
Wood Frame 6/12/2023 Partial Approval JOHN HAYES
Deputy Wood Construction 6/13/2023 Conditional Approval MICHAEL SMITH
Deputy Wood Construction 8/4/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 9/25/2023 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 9/25/2023 Approved JOHN HAYES
Green Building Rough 9/25/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/25/2023 Approved JOHN HAYES
MERV13>=Rough 9/25/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/25/2023 Approved JOHN HAYES
Sewer 9/25/2023 Partial Approval JOHN HAYES
Wood Frame 9/25/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/16/2023 Approved JOHN HAYES
Green Building Rough 10/16/2023 Approved JOHN HAYES
MERV13>=Rough 10/16/2023 Approved JOHN HAYES
Wood Frame 10/16/2023 Approved JOHN HAYES
Insulation 10/23/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 10/23/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 11/17/2023 Approved KEVIN BERBERYAN
Final 11/27/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/27/2023 Approved CHRISTOPHER ROJAS
Grading Pre-Inspection 8/19/2024 No Access for Inspection JOSE AVILA
Pool Piping 8/19/2024 No Access for Inspection JOSE AVILA
Pool/Spa Cover 8/19/2024 No Access for Inspection JOSE AVILA
ELECTRICAL-Final 12/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 12/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/2/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 12/2/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 12/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
MERV13>=Final 12/2/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 12/2/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 12/2/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 12/16/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Gas Test 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
MERV13>=Final 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Final 12/18/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 12/18/2024 Approved ROBERTO PALACIOS-LOPEZ