6535 N BELLINGHAM AVE 91606
Certificate Information: 6535 N BELLINGHAM AVE 91606
- Application / Permit
- 22014-20000-02305
- Plan Check / Job No.
- B22VN07283
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 23'8" X 41' IRREGULAR SHAPED FIRSTAND SECOND FLOOR ADDITION TO AND CONVERT (E) 20'2" X 18'2" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)AND(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/6/2022
- Issuing Office
- Current Status
- CofO Issued on 1/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | COLIN LOREDO |
| Corrections Issued | 6/14/2022 | COLIN LOREDO |
| Quality Review Completed | 6/16/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/27/2022 | APPLICANT |
| Applicant returned to address corrections | 8/25/2022 | RARES BODEA |
| Plan Check Approved | 9/6/2022 | RARES BODEA |
| Issued | 9/6/2022 | APPLICANT |
| CofO in Progress | 12/31/2024 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 1/17/2025 | RUBEN SALAS |
| Permit Finaled | 1/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/8/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 7/25/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/27/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 8/2/2022 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/1/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 5/11/2023 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 6/1/2023 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/2/2023 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 6/2/2023 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 6/2/2023 | Not Ready for Inspection | JOHN HAYES |
| Deputy Drilled-In Anchors | 6/12/2023 | Conditional Approval | MICHAEL SMITH |
| Wood Frame | 6/12/2023 | Partial Approval | JOHN HAYES |
| Deputy Wood Construction | 6/13/2023 | Conditional Approval | MICHAEL SMITH |
| Deputy Wood Construction | 8/4/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 9/25/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 9/25/2023 | Approved | JOHN HAYES |
| Green Building Rough | 9/25/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 9/25/2023 | Approved | JOHN HAYES |
| MERV13>=Rough | 9/25/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 9/25/2023 | Approved | JOHN HAYES |
| Sewer | 9/25/2023 | Partial Approval | JOHN HAYES |
| Wood Frame | 9/25/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | JOHN HAYES |
| Green Building Rough | 10/16/2023 | Approved | JOHN HAYES |
| MERV13>=Rough | 10/16/2023 | Approved | JOHN HAYES |
| Wood Frame | 10/16/2023 | Approved | JOHN HAYES |
| Insulation | 10/23/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/23/2023 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 11/17/2023 | Approved | KEVIN BERBERYAN |
| Final | 11/27/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/27/2023 | Approved | CHRISTOPHER ROJAS |
| Grading Pre-Inspection | 8/19/2024 | No Access for Inspection | JOSE AVILA |
| Pool Piping | 8/19/2024 | No Access for Inspection | JOSE AVILA |
| Pool/Spa Cover | 8/19/2024 | No Access for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 12/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 12/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 12/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 12/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Final | 12/2/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 12/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 12/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 12/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/16/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 12/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 12/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| MERV13>=Final | 12/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 12/16/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/18/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 12/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |