14831 W MAYALL ST 91345
Certificate Information: 14831 W MAYALL ST 91345
- Application / Permit
- 22014-20000-02298
- Plan Check / Job No.
- B22VN07271
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION ( 5' X 18' ) TO EX. DETACHED 2-CAR GARAGE AND CONVERT GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 8/19/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 5/14/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| Plan Check Approved | 8/19/2022 | ROSENDO MEDINA |
| Issued | 8/19/2022 | APPLICANT |
| CofO in Progress | 2/24/2023 | JENNIFER RABUCHIN |
| CofO Issued | 3/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/10/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2022 | Partial Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 9/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/5/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Sewer | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 10/5/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/17/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/17/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/28/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 11/3/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/21/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 12/15/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/30/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/31/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/31/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/31/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 1/31/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/31/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/31/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 1/31/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/23/2023 | Approved | JENNIFER RABUCHIN |
| Final | 2/23/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/23/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/23/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2023 | SGSOV Approved | JENNIFER RABUCHIN |