19906 W WELBY WAY 91306

Certificate Information: 19906 W WELBY WAY 91306

Application / Permit
22014-20000-02297
Plan Check / Job No.
B22VN07268
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 307 SQ. FT. BEDROOM AND BATHROOM ON THE FIRST FLOOR, AND A 207 SQ. FT. TRELLIS ADDITION - ALL WORK PER ENGINEER
Permit Issued
Issued on 6/13/2022
Issuing Office
Current Status
CofO Issued on 3/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 DANIEL ABRAMYAN
Corrections Issued 5/12/2022 DANIEL ABRAMYAN
Plan Check Approved 5/12/2022 DANIEL ABRAMYAN
Building Plans Picked Up 6/2/2022 APPLICANT
Issued 6/13/2022 APPLICANT
CofO in Progress 10/7/2022 DAVID SANDOVAL
Permit Finaled 3/9/2023 DANIEL ORRANTE
CofO Issued 3/9/2023 DANIEL ORRANTE
Permit Finaled 3/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/16/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 5/16/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/16/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/18/2022 Partial Approval STEVEN BACK
Footing/Foundation/Slab 7/18/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 7/28/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 7/28/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Approved STEVEN BACK
Insulation 8/16/2022 Not Ready for Inspection STEVEN BACK
Rough-Elec/Plmb/HVAC 8/16/2022 Approved STEVEN BACK
Insulation 8/17/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 8/19/2022 Partial Approval STEVEN BACK
Green Building Rough 8/19/2022 Approved STEVEN BACK
Interior/Exterior Lathing 8/19/2022 Partial Approval STEVEN BACK
Shower Pan 8/19/2022 Approved STEVEN BACK
Insulation 8/22/2022 Corrections Issued STEVEN BACK
Drywall Nailing 8/24/2022 Corrections Issued STEVEN BACK
Insulation 8/24/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 8/24/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 9/14/2022 Not Ready for Inspection STEVEN BACK
Final 9/14/2022 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 9/14/2022 Not Ready for Inspection STEVEN BACK
Green Building Final 9/14/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 9/14/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 10/6/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 10/6/2022 Approved DAVID SANDOVAL
Final 10/6/2022 OK to Issue CofO DAVID SANDOVAL
Footing/Foundation/Slab 10/6/2022 Approved DAVID SANDOVAL
Green Building Final 10/6/2022 Approved DAVID SANDOVAL
HVAC-Final 10/6/2022 Approved DAVID SANDOVAL
PLUMBING-Final 10/6/2022 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 10/6/2022 Approved DAVID SANDOVAL