429 N ARDEN BLVD 90004

Certificate Information: 429 N ARDEN BLVD 90004

Application / Permit
22014-20000-02295
Plan Check / Job No.
B22VN07264
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 441 SF TO 2ND FLOOR OF (E) 2-STORY SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 6/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 COLIN LOREDO
Corrections Issued 6/16/2022 COLIN LOREDO
Quality Review Completed 6/16/2022 OMID HEDAYAT
Building Plans Picked Up 6/17/2022 APPLICANT
Plan Check Approved 7/14/2022 COLIN LOREDO
Issued 7/14/2022 APPLICANT
CofO in Progress 6/20/2023 JEFFREY MEAD
CofO Issued 6/25/2023 DEROLD HAUFF
Permit Finaled 6/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/23/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/27/2022 JEANIE LAM
Sewer availability Cleared 6/27/2022 JEANIE LAM

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Creative Home Remodeling Group Inc; Lic. No.: 943341-B 11333 MOORPARK ST #214      STUDIO CITY, CA 91602
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/8/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 8/9/2022 Corrections Issued JEFFREY MEAD
METHANE-Barrier 8/9/2022 Not Ready for Inspection JEFFREY MEAD
METHANE-Subgrade 8/9/2022 Not Ready for Inspection JEFFREY MEAD
Footing/Foundation/Slab 8/12/2022 Approved JEFFREY MEAD
METHANE-Barrier 8/12/2022 Approved JEFFREY MEAD
METHANE-Subgrade 8/12/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Partial Approval JEFFREY MEAD
PLUMBING-Rough 8/31/2022 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval JEFFREY MEAD
Green Building Rough 9/7/2022 Not Ready for Inspection JEFFREY MEAD
METHANE-Rough 9/7/2022 Approved JEFFREY MEAD
Wood Frame 9/7/2022 Not Ready for Inspection JEFFREY MEAD
Deputy Wood Construction 9/14/2022 Partial Approval JEFFREY MEAD
Drywall Nailing 10/11/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Rough 10/11/2022 Not Ready for Inspection JEFFREY MEAD
Rough-Elec/Plmb/HVAC 10/11/2022 Approved JEFFREY MEAD
Wood Frame 10/17/2022 Approved JEFFREY MEAD
Insulation 11/2/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 11/2/2022 Approved JEFFREY MEAD
Shower Pan 11/2/2022 Approved JEFFREY MEAD
Drywall Nailing 11/17/2022 Approved JEFFREY MEAD
Green Building Rough 11/17/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 1/31/2023 Approved JEFFREY MEAD
Final 1/31/2023 Corrections Issued JEFFREY MEAD
Green Building Final 1/31/2023 Partial Approval JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 1/31/2023 Partial Approval JEFFREY MEAD
Final 3/10/2023 Corrections Issued JEFFREY MEAD
Green Building Final 3/10/2023 No Access for Inspection JEFFREY MEAD
Smoke Detectors 3/10/2023 No Access for Inspection JEFFREY MEAD
Final 5/15/2023 Corrections Issued JEFFREY MEAD
ELECTRICAL-Final 6/20/2023 Approved JEFFREY MEAD
Final 6/20/2023 OK to Issue CofO JEFFREY MEAD
Green Building Final 6/20/2023 Approved JEFFREY MEAD
HVAC-Final 6/20/2023 Approved JEFFREY MEAD
PLUMBING-Final 6/20/2023 Approved JEFFREY MEAD
Smoke Detectors 6/20/2023 Approved JEFFREY MEAD