17140 W RANCHO ST 91316

Certificate Information: 17140 W RANCHO ST 91316

Application / Permit
22014-20000-02292
Plan Check / Job No.
B22VN07258
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 1ST AND 2ND FLOOR TO (E) 2 STORY BUILDING AND TO RELOCATE GARAGE LOCAITON
Permit Issued
Issued on 10/19/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 TROY DEGUZMAN
Corrections Issued 6/8/2022 TROY DEGUZMAN
Quality Review Completed 6/8/2022 OMID HEDAYAT
Applicant returned to address corrections 8/28/2022 MOHAMMAD ESMAILI
Plan Check Approved 10/17/2022 MOHAMMAD ESMAILI
Issued 10/19/2022 APPLICANT
CofO in Progress 5/25/2023 VINCENT HANLEY
Permit Finaled 5/30/2023 JOHN JANSON
CofO Issued 5/30/2023 JOHN JANSON
Permit Finaled 5/30/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/8/2022 ALEXANDER HELFER
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 6/16/2022 CARLOS AGUILERA
Watercourse Cleared 6/16/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/21/2022 CARLOS AGUILERA
Sewer availability Cleared 6/21/2022 CARLOS AGUILERA
Miscellaneous Cleared 7/19/2022 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 7/25/2022 LAVEON RIDER
Low Impact Development Cleared 8/12/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/15/2022 CARLOS AGUILERA
Green Code Cleared 8/25/2022 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/1/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 11/1/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/16/2022 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 12/16/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval VINCENT HANLEY
Green Building Rough 12/16/2022 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 12/16/2022 Approved VINCENT HANLEY
PLUMBING-Rough 12/16/2022 Corrections Issued VINCENT HANLEY
Deputy Wood Construction 12/20/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/21/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Approved VINCENT HANLEY
Gas Test 12/21/2022 Corrections Issued VINCENT HANLEY
Green Building Rough 12/21/2022 Approved VINCENT HANLEY
Insulation 12/21/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/21/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 12/21/2022 Partial Approval VINCENT HANLEY
Gas Test 12/30/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/30/2022 Partial Approval VINCENT HANLEY
Drywall Nailing 1/17/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 1/17/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/17/2023 Approved VINCENT HANLEY
PLUMBING-Rough 1/17/2023 Approved VINCENT HANLEY
Shower Pan 1/17/2023 Approved VINCENT HANLEY
Final 2/17/2023 Corrections Issued VINCENT HANLEY
Green Building Final 2/17/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Approved VINCENT HANLEY
Smoke Detectors 2/17/2023 Approved VINCENT HANLEY
Final 3/3/2023 Corrections Issued VINCENT HANLEY
Special/Order Compliance 3/3/2023 Partial Inspection JESUS PINEDA
Special/Order Compliance 5/8/2023 Corrections Issued STEVEN BACK
Final 5/25/2023 OK to Issue CofO VINCENT HANLEY