7532 N BECK AVE 91605

Certificate Information: 7532 N BECK AVE 91605

Application / Permit
22014-20000-02274
Plan Check / Job No.
B22VN07221
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 12/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2022 APPLICANT
Assigned to Plan Check Engineer 5/16/2022 JEFFREY TANGONAN
Corrections Issued 5/16/2022 JEFFREY TANGONAN
Applicant returned to address corrections 7/13/2022 JEFFREY TANGONAN
Building Plans Picked Up 7/19/2022 APPLICANT
Applicant returned to address corrections 11/29/2022 ANGELICA DAVE
Applicant returned to address corrections 12/2/2022 JESSE ARELLANO
Plan Check Approved 12/7/2022 FERNANDO FLORES
Issued 12/20/2022 APPLICANT
CofO in Progress 12/22/2023 JOHN HAYES
Permit Finaled 3/28/2024 DANIEL ORRANTE
CofO Issued 3/28/2024 DANIEL ORRANTE
Permit Finaled 3/28/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/7/2022 JOSE DUARTE-DIAZ
Permit Cleared 6/7/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/8/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/8/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 9/30/2022 MITESH PATEL
Construction near power lines Cleared 10/12/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 11/9/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/2/2023 Corrections Issued JOHN HAYES
Underground Mechanical 3/21/2023 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/5/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 8/1/2023 Partial Approval JOHN HAYES
Green Building Rough 8/1/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 8/1/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 8/1/2023 Corrections Issued JOHN HAYES
Verify Sprinkler Sign Off 8/1/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 8/7/2023 Approved JOHN HAYES
Deputy Wood Construction 8/7/2023 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 8/7/2023 Approved JOHN HAYES
Green Building Rough 8/7/2023 Approved JOHN HAYES
HVAC-Rough 8/7/2023 Approved JOHN HAYES
PLUMBING-Rough 8/7/2023 Approved JOHN HAYES
Insulation 8/14/2023 Approved JOHN HAYES
Interior/Exterior Lathing 8/14/2023 Partial Approval JOHN HAYES
Drywall Nailing 8/21/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 8/21/2023 Approved THOMAS FINNILA
ELECTRICAL-Rough 10/24/2023 Not Ready for Inspection ROBERT GOLD
Underground Mechanical 10/24/2023 Approved ROBERT GOLD
Final 11/9/2023 Corrections Issued JOHN HAYES
Green Building Final 11/9/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved JOHN HAYES
Service/Power Release 11/9/2023 Not Ready for Inspection JOHN HAYES
Smoke Detectors 11/9/2023 Approved JOHN HAYES
ELECTRICAL-Final 12/7/2023 Approved JOHN HAYES
Final 12/22/2023 OK to Issue CofO JOHN HAYES
Service/Power Release 12/22/2023 Approved JOHN HAYES