8333 1/2 S BARNSLEY AVE 90045

Certificate Information: 8333 1/2 S BARNSLEY AVE 90045

Application / Permit
22014-20000-02243
Plan Check / Job No.
B22VN07150
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 7'-0" x 20'-0" TO AND CONVERT THE 18'-0" x 20'-0" (E)DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 10/6/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 5/20/2022 SARKIS HARABEDIAN
Corrections Issued 5/21/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 6/24/2022 PINANK PATEL
Plan Check Approved 7/24/2022 SARKIS HARABEDIAN
Building Plans Picked Up 7/26/2022 APPLICANT
Issued 10/6/2023 APPLICANT
CofO in Progress 4/30/2024 BOBBY KEY
Permit Finaled 5/1/2024 DANIEL ORRANTE
CofO Issued 5/1/2024 DANIEL ORRANTE
Permit Finaled 5/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/31/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 6/2/2022 JENSON LEE
Roof/Waste drainage to street Cleared 6/2/2022 JENSON LEE
Sewer availability Cleared 6/2/2022 JENSON LEE
Grading Pre-Inspection Cleared 6/3/2022 ALEXANDER HELFER
Specific Plan Cleared 6/14/2022 PEDRO AYALA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Leigh Construction; Lic. No.: 782532-B 6511 81ST      LOS ANGELES, CA 90045
Contractor Skyline Construction And Remodeling; Lic. No.: 859873-B 21777 VENTURA BLVD #242      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/24/2023 Partial Approval BOBBY KEY
Sewer 10/24/2023 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 11/1/2023 Approved BOBBY KEY
Underground Mechanical 11/1/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Approved BOBBY KEY
ELECTRICAL-Rough 1/4/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Approved BOBBY KEY
Green Building Rough 1/4/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 1/4/2024 Approved BOBBY KEY
PLUMBING-Rough 1/4/2024 Approved BOBBY KEY
Shower Pan 1/4/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 1/11/2024 Approved BOBBY KEY
Green Building Rough 1/11/2024 Approved BOBBY KEY
Interior/Exterior Lathing 1/11/2024 Partial Approval BOBBY KEY
Insulation 1/12/2024 Approved BOBBY KEY
Drywall Nailing 1/18/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 1/26/2024 Approved BOBBY KEY
Shower Pan 1/26/2024 Approved BOBBY KEY
Gas Test 2/28/2024 Approved BOBBY KEY
ELECTRICAL-Final 3/20/2024 Conditional Approval BOBBY KEY
Final 3/20/2024 Corrections Issued BOBBY KEY
Green Building Final 3/20/2024 Approved BOBBY KEY
HVAC-Final 3/20/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 3/20/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Not Ready BOBBY KEY
Smoke Detectors 3/20/2024 Approved BOBBY KEY
ELECTRICAL-Final 4/30/2024 Approved BOBBY KEY
Final 4/30/2024 OK to Issue CofO BOBBY KEY
HVAC-Final 4/30/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/30/2024 SGSOV Approved BOBBY KEY
Service/Power Release 4/30/2024 Approved BOBBY KEY