7318 N AMESTOY AVE 91406

Certificate Information: 7318 N AMESTOY AVE 91406

Application / Permit
22014-20000-02237
Plan Check / Job No.
B22VN07140
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan 187 SF PROPOSED ADDITION AT REAR OF EXISTING SINGLE FAMILY RESIDENCE. NEW WALK-IN CLOSET AND NEW MASTER BATHROOM PER WFPP
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2022 APPLICANT
Assigned to Plan Check Engineer 5/9/2022 SUNMIN LEE
Corrections Issued 5/12/2022 SUNMIN LEE
Applicant returned to address corrections 6/13/2022 SUNMIN LEE
Plan Check Approved 6/21/2022 SUNMIN LEE
Issued 6/21/2022 APPLICANT
CofO in Progress 11/23/2022 RAUL OLAGI
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/15/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/15/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/15/2022 DAGOVERTO GUERRERO

Contact Information

Contractor M D M Custom Remodeling Inc; Lic. No.: 930166-B       ,
Contractor Mdm General Contractor Room Additions; Lic. No.: 930166-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2022 Approved ALAN MORELOS
Special/Order Compliance 7/27/2022 Corrections Issued ALAN MORELOS
Deputy Drilled-In Anchors 7/29/2022 Approved ALAN MORELOS
PLUMBING-Rough 8/2/2022 Partial Approval RAUL OLAGI
Wood Frame 8/2/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Approved RAUL OLAGI
Insulation 8/4/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 8/18/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Not Ready for Inspection RAUL OLAGI
Green Building Rough 8/18/2022 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 8/18/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 8/26/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 8/26/2022 Approved RAUL OLAGI
HVAC-Rough 8/26/2022 Approved RAUL OLAGI
PLUMBING-Rough 8/26/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 9/14/2022 Approved RAUL OLAGI
Green Building Rough 9/14/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 9/14/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 9/14/2022 Approved RAUL OLAGI
Insulation 9/16/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 9/16/2022 Approved RAUL OLAGI
Shower Pan 9/16/2022 Approved RAUL OLAGI
Drywall Nailing 9/29/2022 Approved RAUL OLAGI
Final 11/22/2022 OK to Issue CofO RAUL OLAGI
Green Building Final 11/22/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 11/22/2022 Approved RAUL OLAGI