6447 N GREENBUSH AVE 91401

Certificate Information: 6447 N GREENBUSH AVE 91401

Application / Permit
22014-20000-02191
Plan Check / Job No.
B22VN06919
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU AND SECOND STORY ADDITION TO ADU PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 8/18/2022
Issuing Office
Current Status
CofO Issued on 3/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2022 APPLICANT
Assigned to Plan Check Engineer 5/23/2022 VIVIAN LAO
Corrections Issued 5/24/2022 VIVIAN LAO
Quality Review Completed 6/8/2022 MICHAEL PEREZ
Plan Check Approved 8/11/2022 VIVIAN LAO
Issued 8/18/2022 APPLICANT
CofO in Progress 3/8/2023 KIRK SANDERS
CofO Issued 3/28/2023 MICHAEL SMITH
Permit Finaled 3/28/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/24/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/24/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/27/2022 MEGAN GODINEZ
Sewer availability Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/27/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/27/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2022 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 9/16/2022 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 9/21/2022 Not Ready for Inspection RAFAEL CORTES
Structural Steel Frame 9/21/2022 Not Ready for Inspection RAFAEL CORTES
Underground Mechanical 9/21/2022 Approved RAFAEL CORTES
Deputy Drilled-In Anchors 9/22/2022 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 9/22/2022 Corrections Issued ALAN MORELOS
Deputy Reinf. Concrete 9/26/2022 Conditional Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 9/26/2022 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Corrections Issued RAFAEL CORTES
Deputy Wood Construction 10/13/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Partial Approval CALEB MEISTER
BUILDING-Rough-Frame 10/25/2022 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 10/25/2022 Corrections Issued CALEB MEISTER
Green Building Rough 10/25/2022 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 10/25/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 10/25/2022 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 11/1/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 11/1/2022 Approved MISAEL ESPARZA
Green Building Rough 11/1/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 11/1/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 11/1/2022 Approved MISAEL ESPARZA
Shower Pan 11/1/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/10/2022 Partial Approval CHRISTOPHE COCHRAN
Insulation 11/14/2022 Approved CALEB MEISTER
Drywall Nailing 11/21/2022 Approved WILLIAM WREN
Gas Test 11/21/2022 Approved WILLIAM WREN
Green Building Rough 11/21/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 11/21/2022 Partial Approval WILLIAM WREN
Interior/Exterior Lathing 11/30/2022 Approved KIRK SANDERS
ELECTRICAL-Final 2/24/2023 Corrections Issued KIRK SANDERS
Final 2/24/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 2/24/2023 Approved KIRK SANDERS
Gas Test 2/24/2023 Corrections Issued KIRK SANDERS
Green Building Final 2/24/2023 Approved KIRK SANDERS
HVAC-Final 2/24/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 2/24/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready KIRK SANDERS
Service/Power Release 2/24/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 2/24/2023 Approved KIRK SANDERS
ELECTRICAL-Final 2/28/2023 Approved KIRK SANDERS
Gas Test 2/28/2023 Approved KIRK SANDERS
HVAC-Final 2/28/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 2/28/2023 Approved KIRK SANDERS
Service/Power Release 2/28/2023 Not Ready for Inspection KIRK SANDERS
Final 3/7/2023 OK to Issue CofO KIRK SANDERS
HVAC-Final 3/7/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 3/7/2023 Approved KIRK SANDERS