5214 N ARGUS DR 90041

Certificate Information: 5214 N ARGUS DR 90041

Application / Permit
22014-20000-02188
Plan Check / Job No.
B22VN06909
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (57'-4"x 35'-4") IRR SHAPE WITH PATIO COVER @ 1ST FLOOR & ADD 3'-6" X 13' TO AND CONVERT(E) ATTIC SPACE TO HABITABLE 2ND FLOOR TO (E) SINGLE FAMILY DWELLING, NFPA-13D FIRE SPRINKLER THROUGHOUT
Permit Issued
Issued on 9/2/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 TROY DEGUZMAN
Corrections Issued 6/3/2022 TROY DEGUZMAN
Quality Review Completed 6/3/2022 OMID HEDAYAT
Building Plans Picked Up 6/17/2022 APPLICANT
Plan Check Approved 8/25/2022 SELLA BENYAMIN
Issued 9/2/2022 APPLICANT
CofO in Progress 8/20/2025 CRAIG VAUGHAN
Permit Finaled 8/21/2025 DEROLD HAUFF
CofO Issued 8/21/2025 DEROLD HAUFF
Permit Finaled 8/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/2/2022 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 7/1/2022 CELINA MORENO
Sewer availability Cleared 7/1/2022 CELINA MORENO
Hydrant and Access approval Cleared 7/22/2022 KURT CORRAL
Low Impact Development Cleared 8/2/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 8/5/2022 JEANIE LAM

Contact Information

Contractor Opus Builders Inc; Lic. No.: 1059646-B 5244 VINELAND AVENUE      NORTH HOLLYWOOD, CA 91601
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2022 Approved CRAIG VAUGHAN
Deputy Drilled-In Anchors 10/31/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 11/16/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 11/16/2022 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 2/1/2023 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/3/2023 Approved CRAIG VAUGHAN
HVAC-Rough 3/3/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/3/2023 Partial Approval CRAIG VAUGHAN
Wood Frame 3/3/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/6/2023 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 3/6/2023 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 3/6/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 3/8/2023 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 3/8/2023 Partial Approval CRAIG VAUGHAN
Verify Sprinkler Sign Off 3/8/2023 Approved CRAIG VAUGHAN
Insulation 3/15/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/15/2023 Partial Approval CRAIG VAUGHAN
Drywall Nailing 3/31/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/6/2023 Approved CHARLES BOGHOSKHAN
Shower Pan 4/6/2023 Approved CHARLES BOGHOSKHAN
Final 10/6/2023 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 10/6/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/6/2023 Approved CRAIG VAUGHAN
Gas Test 10/11/2023 Approved CRAIG VAUGHAN
Final 10/23/2023 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 3/29/2024 Approved CRAIG VAUGHAN
Final 3/29/2024 Conditional Approval CRAIG VAUGHAN
HVAC-Final 3/29/2024 Approved CRAIG VAUGHAN
PLUMBING-Final 3/29/2024 Approved CRAIG VAUGHAN
Final 8/19/2025 OK to Issue CofO CRAIG VAUGHAN