1271 E 40TH PL 90011
Certificate Information: 1271 E 40TH PL 90011
- Application / Permit
- 22014-20000-02119
- Plan Check / Job No.
- B22VN06751
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 3' X 20' PORTION OF GARAGE, ADD IRR. 30' X 40' TO AND CONVERT THE (E) DET. GARAGE TO A (N) 30' X 40' ACCESSORY DWELLING UNIT PER LAMC SEC 12.22A33(c) AND (d).
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Current Status
- CofO Issued on 4/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | PINANK PATEL |
| Corrections Issued | 5/8/2022 | PINANK PATEL |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Issued | 8/4/2022 | APPLICANT |
| CofO in Progress | 1/11/2024 | STUART CHAPMAN |
| CofO Issued | 4/5/2024 | DEROLD HAUFF |
| Permit Finaled | 4/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2022 | CINDY QI |
| Sewer availability | Cleared | 5/16/2022 | CINDY QI |
| Address approval | Cleared | 5/27/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 7/21/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/23/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/15/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Pre-Inspection | 9/15/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 11/1/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 11/1/2022 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Conditional Approval | BRENDAN MORELLI |
| Gas Test | 12/19/2022 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 12/19/2022 | Partial Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 12/19/2022 | Approved | BRENDAN MORELLI |
| Wood Frame | 12/19/2022 | Partial Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/11/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/11/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 1/11/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 1/11/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/30/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/30/2023 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Corrections Issued | BRENDAN MORELLI |
| Sewer | 1/30/2023 | Approved | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 2/17/2023 | Conditional Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 3/6/2023 | Corrections Issued | HORACE FULTZ |
| Masonry Wall/Backfill | 3/6/2023 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 3/7/2023 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/10/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 3/10/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 3/10/2023 | Approved | BRENDAN MORELLI |
| Insulation | 3/17/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 4/5/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/5/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 4/5/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 8/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/9/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 11/9/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 11/9/2023 | Approved | STUART CHAPMAN |
| Final | 1/10/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/11/2024 | Approved | STUART CHAPMAN |
| Final | 1/11/2024 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 1/11/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 1/11/2024 | Approved | STUART CHAPMAN |