13713 N NORRIS AVE 91342
Certificate Information: 13713 N NORRIS AVE 91342
- Application / Permit
- 22014-20000-02116
- Plan Check / Job No.
- B22VN06744
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRR. SHAPED 19'-6" x 30' ADDITION TO (E) DET. GARAGE TO ENLARGE GARAGE, ADD ONE NEW PARKING SPACE AND STORAGE AREA, AND ADD NEW 2ND FLOOR 23" x 44' ACCESSORY DWELLING UNIT OVER GARAGE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | SEAN SHAHMIRI |
| Corrections Issued | 5/27/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 6/6/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Applicant returned to address corrections | 1/5/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 2/6/2023 | SEAN SHAHMIRI |
| Issued | 2/14/2023 | APPLICANT |
| CofO in Progress | 2/22/2024 | CRAIG DAVIS |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/17/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/4/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/22/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/22/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/22/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2023 | Partial Inspection | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 4/11/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 4/13/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/28/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 6/20/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 6/29/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 7/18/2023 | Not Ready for Inspection | ROBERT GOLD |
| Wood Frame | 7/18/2023 | Not Ready for Inspection | ROBERT GOLD |
| ELECTRICAL-Rough | 7/24/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 7/24/2023 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 7/24/2023 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 7/24/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 7/27/2023 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Rough | 7/27/2023 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/7/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 8/7/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/7/2023 | Conditional Approval | DAVID ANDERSON |
| Insulation | 8/7/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 8/17/2023 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 9/20/2023 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 12/13/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 12/13/2023 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/13/2023 | Approved | KEVIN BERBERYAN |
| Green Building Final | 12/13/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 12/13/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Final | 12/13/2023 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 12/13/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 2/16/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 2/16/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 2/16/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 2/21/2024 | Approved | CRAIG DAVIS |
| Final | 2/21/2024 | OK to Issue CofO | CRAIG DAVIS |
| Green Building Final | 2/21/2024 | Approved | CRAIG DAVIS |
| HVAC-Final | 2/21/2024 | Approved | CRAIG DAVIS |
| Smoke Detectors | 2/21/2024 | Approved | CRAIG DAVIS |
| Service/Power Release | 3/12/2024 | Corrections Issued | KEVIN BERBERYAN |