6703 N COSTELLO AVE 91405
Certificate Information: 6703 N COSTELLO AVE 91405
- Application / Permit
- 22014-20000-02107
- Plan Check / Job No.
- B22VN06697
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT (E) STORAGE, GARAGE AND PATIO INTO A (N) ACCESSORY DWELLING UNIT with PATIO PER LAMC 12.22 A.33(c) and (d). "Comply with department order. Permit will expire 30 days from issuance date."
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 5/9/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 10/5/2022 | RAHEL BEYENE |
| Building Plans Picked Up | 10/5/2022 | APPLICANT |
| Plan Check Approved | 10/12/2022 | RICARDO RAMIREZ |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 6/23/2023 | RYAN SALAZAR |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 5/10/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/11/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 9/29/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/18/2022 | Partial Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 11/28/2022 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/15/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 2/15/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/15/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 2/15/2023 | Approved | RAUL OLAGI |
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/27/2023 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 2/27/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 2/27/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/27/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/6/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 3/6/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/6/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/6/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 3/6/2023 | Approved | RYAN SALAZAR |
| Insulation | 3/13/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/13/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/16/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 3/22/2023 | Approved | RYAN SALAZAR |
| Final | 6/14/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/14/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 6/14/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 6/14/2023 | Approved | RYAN SALAZAR |
| Final | 6/23/2023 | OK to Issue CofO | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Approved | RYAN SALAZAR |